RERA ID: P51700030533
Project Name: Runwal Gardens Phase 4 Bldg No. 33-34
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-06-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Dombivali, Village Gharivali Usarghar Sagaon, , Kalyan, Thane-421204

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
SURVEY NOS 4/5PT, 5/1PT, 5/2PT, 5/3PT, 5/4PT, 5/5PT, 5/6PT, 44/11PT, 44/12PT OF VILLAGE GHARIVALI

Boundaries:
R G Area
Bldg No 31 and 32N Bldg No 35 and 36
WE
S
24 Meters wide Road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1475 sq.mt.
Sanctioned Built-up Area: 47786 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 68
No. of basements: 2
No. of Plinths: 2
No. of Stilts: 2

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 440 sq ft 4 0
2BHK 560 to 646 sq ft 316 230
3BHK 752 to 759 sq ft 54 49
Others 488 to 668 sq ft 190 151
Project Developer:
Runwal Residency Private Limited
Organization Type: Company

Address: 4Th Floor, Runwal & Omkar Esquare, Opp. Sion Chunabhatti Signal, Off: Eastern Exp. Highway,, Sion East, Chunabhatti Signal, Mumbai City-400022

Office Phone: +91 22611 62000


Member details:
Member Name Designation
Vijay Kisan Patil Director
Saurabh Shankar Natu Authorized Signatory
Lucy Roychoudhury Director
Subodh Subhash Runwal Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Ar Sandeep Prabhu for Sakaar Architect
Chetan Sampat Engineer
Kshirsagar and Associate Chartered Accountant
Mahimtura Consultant Other Professional
BuroHappold Engineers India Pvt Ltd Other Professional
MEP Consulting Engineers Other Professional
Rugved Architectural Consultancy Other Professional
Epicon Consultant Pvt Ltd Other Professional
Precise Architects and consultants Architect


Projects in the state by this developer:
P51700053843 - Primrose MHADA 2 - Thane
P51700052441 - Runwal Gardens Phase 8 Bldg No. 43 and 45 - Thane
P51700051346 - Runwal Gardens Phase 6A Bldg No. 53-54 - Thane
P51700048175 - Runwal Edge - Thane
P51700047512 - Runwal Gardens - Phase 8 - Bldg No. 44 - Thane
P51700046550 - Runwal Gardens Phase 4 Bldg No. 38 - Thane
P51700033206 - Runwal Gardens Phase 4 Bldg No. 37 - Thane
P51700031609 - Runwal Gardens Phase 5 Bldg No. 39 to 42 - Thane
P51700031319 - Runwal Gardens Phase 4 Bldg No. 35-36 - Thane
P51700030533 - Runwal Gardens Phase 4 Bldg No. 33-34 - Thane
…and 8 more
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Runwal Gardens Phase 4: A New Chapter in Luxurious Living

Runwal Gardens Phase 4, located in the thriving locality of Dombivali, Thane, is set to redefine urban living with its meticulously designed residential project. Developed by Runwal Residency Private Limited, this new project, registered under RERA ID: P51700030533, promises a harmonious blend of modern architecture, world-class amenities, and a strategic location.

Situated on a sprawling plot spanning 1475 sq mts, Runwal Gardens Phase 4 comprises two impressive buildings (Bldg No. 33-34), reaching a towering height of 68 floors. With a sanctioned FSI of 47786, the project offers a diverse range of meticulously designed living spaces, catering to the varied needs of discerning homebuyers. From compact 1BHKs (440 sq ft) to spacious 3BHKs (752 to 759 sq ft), and a selection of unique configurations, the project ensures a home for every lifestyle.

Runwal Gardens Phase 4 boasts an exceptional location, offering easy access to key amenities and transportation hubs. Situated in the heart of Dombivali, the project benefits from excellent connectivity to major thoroughfares, including the 24-meter wide road running south of the property.

Furthermore, the project is strategically positioned near various social infrastructure, including schools, healthcare facilities, and shopping malls, ensuring a convenient and comfortable lifestyle for residents.

Beyond the physical features, Runwal Gardens Phase 4 offers a host of amenities designed to enhance the living experience. With two basements, two plinths, and two stilts, the project provides ample space for parking and other essential services. The project is also committed to environmental sustainability, evident in its thoughtful design and efficient utilization of space.

With an anticipated completion date of June 30th, 2025, Runwal Gardens Phase 4 is poised to become a landmark residential project in Dombivali. The project’s emphasis on quality construction, thoughtful design, and an array of amenities promises a fulfilling and enriching lifestyle for its residents.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2.5 BHK 62.1 34 28
2BHK 54.77 68 54
2BHK 59.12 60 26
2BHK 60.04 68 61

 

New documents listed below were uploaded to the Documents section:

  • 2 Commencement Certificates / NA Order for plotted development
  • 4 Disclosure of sold/ booked inventory
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 84
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 35
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5
2 X number of Slabs of Super Structure 56
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 13
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 15
2 Overall Percentage of Completion of the work done For the entire Building /Wing 49.9

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 65
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 21
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 25
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
1 Overall Percentage of Completion of the work done For the entire Building /Wing 54.1
2 X number of Slabs of Super Structure 40
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 12
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
2 Overall Percentage of Completion of the work done For the entire Building /Wing 47.7

 

New documents listed below were uploaded to the Documents section:

  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 52.11 30 25
2BHK 54.58 56 35
2BHK 54.77 68 58
2BHK 59.12 60 28
2BHK 60.04 68 57

 

New documents listed below were uploaded to the Documents section:

  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 46
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 20
1 Overall Percentage of Completion of the work done For the entire Building /Wing 49.6
2 X number of Slabs of Super Structure 25
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 10
2 Overall Percentage of Completion of the work done For the entire Building /Wing 45.5

 

New documents listed below were uploaded to the Documents section:

  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 X number of Podiums 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 40.9

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2.5 BHK 61.84 30 23
2.5 BHK 62.1 34 27
2BHK 52.11 30 24
2BHK 54.58 56 33
2BHK 54.77 68 55
2BHK 59.12 60 27
2BHK 60.04 68 56
3BHK 69.88 26 22
3BHK 70.55 28 27

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [5]
  • Building Plan Approval / NA Order for plotted development [38]
  • CERSAI details [3]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances [2]
  • Disclosure of sold/ booked inventory [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [6]
  • Proforma of Allotment letter
  • Status of Formation of Legal Entity (Society/Co Op etc.) [4]