MH
Thane
P51700008458
RERA ID: P51700008458
Project Name: Shivani Heritage
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2020-09-30
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2019-03-31, 2017-12-31).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Thane, Navi Mumbai (M Corp.)-400701

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
28/3

Boundaries:
27-1
29-1N 28-4
WE
S
27

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 6660 sq.mt.
Sanctioned Built-up Area: 12500 sq.mt.
Recreational Open Space: 100 sq.mt.
No. of Buildings sanctioned: 7
No. of Floors sanctioned: 28
No. of Plinths: 7
No. of Stilts: 7
No. of Closed Parking: 122

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 275 to 326 sq ft 106 106
1RK 162 to 549 sq ft 50 49
2BHK 447 to 449 sq ft 20 20
Project Developer:
Gajanan Shyamrao Khabale c/o Shyamrao Narayan Khabale
Organization Type: Individual

Address: 416, 5Th Floor, Central Facility Building, Apmc Fruit Market, Sec 19, Turbhe, Anti Curroption Bureau, Navi Mumbai (M Corp.), Thane-400705

Office Phone: +91 22278 32424
Website URL: www.bhagyashreebuildersanddevelopers.com


Other Professionals involved:
Professional Name Professional Type
Mandar V. Bodhankar Architect
Ram Marathe Engineer
Umesh Thamke Other Professional
Sreedhar Murty Other Professional


Projects in the state by this developer:
P52000050795 - Jai Malhar Apartment Phase II - Raigarh
P52000048891 - Jai Malhar Apartment Phase - I - Raigarh
P52000018661 - JAI MALHAR APARTMENT - Raigarh
P51700008458 - Shivani Heritage - Thane
Litigations

Litigations related to the project ? No

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Architect’s Certificate on Completion of Project (Form 4) [2]
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [9]
  • Certificates of CA (Form 5) [3]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [8]
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [14]
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Other
  • Proforma of Allotment letter
  • Status of Formation of Legal Entity (Society/Co Op etc.)