RERA ID: P51700005256
Project Name: Vaikunth Cluster 4A
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-07-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Balkum, Old Mumbai-Agra Road, Thane (M Corp.), Thane-400608

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
100/24-30,100/31A,31B,100/32-33 of Village Balkum, Taluka, District- Thane

Boundaries:
N274357 E-24925
N225333 E-101360 N237919 E-100839 N248621 E-93460N N236464 E-10696
WE
S
N205250 E-93819

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 3421 sq.mt.
Sanctioned Built-up Area: 29739 sq.mt.
Recreational Open Space: 166 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 80
No. of basements: 2
No. of Plinths: 2
No. of Podiums: 10
No. of Closed Parking: 582

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 495 to 527 sq ft 583 565
Project Developer:
Piramal Estate Private Limited
Organization Type: Company

Address: 8Th Floor, Piramal Tower, Ganapat Rao Kadam Marg, Lower Parel West, Peninsula Corporate Park, Mumbai City-400013

Office Phone: +91 22335 14000
Website URL: www.piramalrealty.com


Member details:
Member Name Designation
Nagamallesh Gattu Authorized Signatory
Sejal Bhanose Company Secretory


Other Professionals involved:
Professional Name Professional Type
Scapes Earth Architect
Gleeds Consulting India Pvt Ltd Engineer
Buro Happold Other Professional
D. B. KETKAR & CO. Chartered Accountant


Projects in the state by this developer:
P51700024580 - Vaikunth Cluster 3 Tower 2 - Thane
P51700024023 - Vaikunth Cluster 3 T1 - Thane
P51700005256 - Vaikunth Cluster 4A - Thane
P51700003793 - Vaikunth Cluster 2 - Thane
P51700003535 - Vaikunth Cluster 1 - Thane
P51700003283 - Vaikunth Cluster 4 - Thane
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
Before the Minister For Revenue and Forest RTS 2717/27/PRA KA 1/J-4 Others Suit 2016 Ongoing
Mumbai High Court 83 Others Writ Petition 2015 Ongoing
Before SDO at Thane 55 Civil Appeal 2023 Ongoing
Before Tahasildar 70 Civil Other 2023 ONGOING
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Vaikunth Cluster 4A: A New Residential Development in Thane

Vaikunth Cluster 4A, a new residential project by Piramal Estate Private Limited, is set to redefine urban living in Thane, Maharashtra. Situated in the prime locality of Balkum, this development boasts a strategic location on Old Mumbai-Agra Road, offering seamless connectivity to the city’s key areas. The project is registered with MahaRERA under the ID P51700005256 and is currently under construction, with an expected completion date of July 31, 2024.

A Vision of Modern Living:

Vaikunth Cluster 4A is designed to cater to the aspirations of modern families seeking a blend of comfort, convenience, and luxury. The project spans a total plot area of 3421 sq m and features two buildings rising to 80 floors, offering a range of spacious 2BHK apartments, each meticulously crafted with modern amenities and high-quality finishes. The project’s design includes two basements, two plinths, and 10 podiums, ensuring ample space for both residential and recreational purposes.

Lifestyle Amenities and a Thriving Community:

Vaikunth Cluster 4A is more than just an address; it is a community. The development boasts a plethora of amenities tailored to cater to the diverse needs of its residents, including a dedicated recreational open space spanning 166 sq m. The project also offers a generous 582 closed parking spaces, ensuring the convenience of residents and their guests.

Strategic Location and Seamless Connectivity:

The strategic location of Vaikunth Cluster 4A on Old Mumbai-Agra Road provides residents with easy access to various parts of the city. The project is well-connected to public transport, making commuting a breeze. The proximity to major employment hubs, shopping centers, healthcare facilities, and educational institutions further enhances the project’s appeal.

Piramal Estate Private Limited: A Trusted Developer:

Vaikunth Cluster 4A is developed by Piramal Estate Private Limited, a renowned and trusted name in the real estate industry. The developer’s commitment to quality, timely delivery, and customer satisfaction is reflected in the project’s meticulous planning and execution.

Noteworthy Points:

  • It is important to note that the project has been flagged with ongoing litigations. Potential buyers should conduct thorough due diligence to understand the implications of these litigations before making any investment decisions.

Conclusion:

Vaikunth Cluster 4A presents a unique opportunity to own a piece of Thane’s thriving real estate landscape. With its strategic location, luxurious amenities, and a reputable developer, this project promises a comfortable, convenient, and fulfilling lifestyle for its residents. However, potential investors should be aware of the ongoing litigations associated with the project and conduct comprehensive research before making any investment decisions.

New documents listed below were uploaded to the Documents section:

  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 20 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 70 Work yet to be started
Fire Protection And Fire Safety Requirements : 100 As per statutory requirements
Electrical Meter Room, Sub-Station, Receiving Station : 100 As per statutory requirements
Water Supply : 100 Work yet to be started
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 STP as part of larger layout
Landscaping & Tree Planting : 60 Work yet to be started
Street Lighting : 50 Work yet to be started
Community Buildings : 90 A part of a larger layout
Treatment And Disposal Of Sewage And Sullage Water : 100 Work yet to be started

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 46 48 47
2BHK 47 377 362
2BHK 48 147 146

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 91
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 87
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 96
1 Overall Percentage of Completion of the work done For the entire Building /Wing 85.9
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 33
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 96
2 Overall Percentage of Completion of the work done For the entire Building /Wing 82.2

 

New documents listed below were uploaded to the Documents section:

  • 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 13 Disclosure of sold/ booked inventory
  • 9 Other

 

There are modifications under Cases section

Court Name Case Number Case Type Petition Name Year Present Status
Before Tahasildar 70 Civil Other 2023 ONGOING

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 47 377 352
2BHK 48 147 139

 

New documents listed below were uploaded to the Documents section:

  • 8 Other
  • 19 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 12 Disclosure of sold/ booked inventory
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
1 Overall Percentage of Completion of the work done For the entire Building /Wing 72.5
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
2 Overall Percentage of Completion of the work done For the entire Building /Wing 73.5

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 60 Work yet to be started
Fire Protection And Fire Safety Requirements : 80 As per statutory requirements
Electrical Meter Room, Sub-Station, Receiving Station : 85 As per statutory requirements
Landscaping & Tree Planting : 40 Work yet to be started
Street Lighting : 30 Work yet to be started
Community Buildings : 70 A part of a larger layout
Treatment And Disposal Of Sewage And Sullage Water : 60 Work yet to be started
Solid Waste Management And Disposal : 100 Work yet to be started
Sewerage (Chamber, Lines, Septic Tank , STP) : 60 STP as part of larger layout

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [15]
  • Building Plan Approval (IOD) [4]
  • CERSAI details
  • Certificates of CA (Form 5) [3]
  • Commencement Certificates / NA Order for plotted development [6]
  • Copy of Layout Approval (in case of layout) [3]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances [5]
  • Disclosure of sold/ booked inventory [11]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [18]
  • Other [7]
  • Proforma of Allotment letter [3]
  • Status of Formation of Legal Entity (Society/Co Op etc.)