MH
Raigarh
P52000052897
RERA ID: P52000052897
Project Name: SIDDHIVINAYAK VIGHNAHARTA
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Pushpak, Plot No 247 Sector R3, Karanjade, Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 247 SECTOR R3, PUSHPAK , NAVI MUMBAI

Boundaries:
STALLS
PLOT NO 246 AND 245N 15 METER WIDE ROAD
WE
S
PLOT NO 248

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 698 sq.mt.
Sanctioned Built-up Area: 2783 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Stilts: 1
No. of Closed Parking: 14

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 15351 sq ft 50 10
1RK 438 sq ft 2 0
2BHK 1107 sq ft 2 0
Shop 1355 sq ft 5 1
Project Developer:
SIDDHIVINAYAK BUILDERS AND DEVELOPERS
Organization Type: Partnership

Address: Office No- 01 And 02, Ananta Complex, Sector - R-4, Plot Number 225, Pushpak Node, Karanjade, Panvel, Raigarh-410206

Office Phone: +91 80808 55532


Member details:
Member Name Designation
AJAY ANANTA PATIL Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
MR BHARAT RATAN NAIK Individual Area Share
BHARATI BHARAT NAIK Individual Area Share
SHRAVAN RATAN NAIK Individual Area Share


Other Professionals involved:
Professional Name Professional Type
ATUL PATEL ARCHITECTS Architect
VIJAY KUMAR SINGH Engineer
G S DESAI AND ASSOCIATES Chartered Accountant


Projects in the state by this developer:
P52000052897 - SIDDHIVINAYAK VIGHNAHARTA - Raigarh
P52100050083 - SHRI SWAMI SAMARTH COMPLEX - Pune
P51700049185 - SIDDHIVINAYAK HOMES - Thane
P51700032591 - RAGHUKUL HEIGHTS - Thane
P51600012992 - OM RESIDENCY APPARTMENT - Nashik
P51500012695 - HANUMAN NAGAR - Aurangabad
P51700011727 - MORESHWAR NAGAR II - Thane
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Siddhivinayak Vighnaharta: A New Residential Project in Navi Mumbai

Siddhivinayak Vighnaharta, a new residential project by Siddhivinayak Builders and Developers, is set to redefine luxury living in Navi Mumbai. Located in the sought-after Pushpak locality, this project promises a serene and comfortable lifestyle amidst modern amenities. With its RERA registration number P52000052897, the project is fully compliant with Maharashtra Real Estate Regulatory Authority (MahaRERA) regulations, ensuring transparency and accountability.

The project spans a total plot area of 698 sq. meters and encompasses a single building with 7 sanctioned floors, including a stilt floor. The project boasts a total sanctioned FSI of 2780, translating into a generous built-up area for residents.

Siddhivinayak Vighnaharta is strategically located in Sector R3 of Pushpak, Navi Mumbai, offering seamless connectivity to key areas. The project enjoys easy access to major transportation hubs, prominent commercial centers, and renowned educational institutions.

Further enhancing the quality of life for residents, the project includes a range of modern amenities such as closed parking for 14 vehicles. This ensures convenience and peace of mind for residents.

A Project Backed by Experienced Developers:

Siddhivinayak Builders and Developers, a well-established partnership firm, brings years of experience and expertise in the real estate sector. Their commitment to quality construction and customer satisfaction is evident in their previous projects, ensuring that Siddhivinayak Vighnaharta will meet the highest standards.

Investing in a Secure Future:

With the project’s completion scheduled for March 31st, 2027, potential investors can be assured of a timely delivery. The project is free from any litigations, providing a secure and risk-free investment opportunity.

Siddhivinayak Vighnaharta offers a unique blend of modern amenities, strategic location, and a trusted developer, making it an ideal choice for discerning homebuyers and investors seeking a comfortable and fulfilling lifestyle in Navi Mumbai.

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 60
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 15
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 52
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 38
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 13
1 Overall Percentage of Completion of the work done For the entire Building /Wing 47.8

 

Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) field under Firm Details section updated with new value 2783.26

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 25 Chambers Lines And Septic Tank To Be Provided

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 20 Chambers Lines And Septic Tank To Be Provided

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 1426.22 50 10
Shop 125.93 5 1

 

New documents listed below were uploaded to the Documents section:

  • 8 Other – Legal
  • 2 Disclosure of sold/ booked inventory
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 50
1 X number of Slabs of Super Structure 50
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 26
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 8
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 4
1 Overall Percentage of Completion of the work done For the entire Building /Wing 33.8

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 Stilt Floor 25
1 Overall Percentage of Completion of the work done For the entire Building /Wing 22.5

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 1426.22 50 0
1RK 40.71 2 0
2BHK 102.93 2 0

 

Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) field under Firm Details section updated with new value 2780.23

 

Number of Sanctioned Floors field under Building/Plot Details section updated with new value 7

 

New documents listed below were uploaded to the Documents section:

  • 3 Building Plan Approval / NA Order for plotted development
  • 3 Copy of Layout Approval (in case of layout)
  • 2 Commencement Certificates / NA Order for plotted development
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development [2]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations [2]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Other – Legal [7]
  • Other – Technical
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]