Project Name: Om Nirman
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-08-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Pushpak- Vadghar, Sector No- R5, Vadghar (Ct), Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Plot No-100, Sector No- R5

Boundaries:
Plot No- 99
Plot No 101N 9 Meter Wide Road
WE
S
9 meter wide road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 319 sq.mt.
Sanctioned Built-up Area: 725 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 11
No. of Closed Parking: 5

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 279 to 306 sq ft 11 10
1RK 197 sq ft 4 2
2BHK 623 sq ft 2 2
Project Developer:
Nirman Infra
Organization Type: Partnership

Address: Plot No-100, Sector No- R5, Vadghar, Sector No-R5, Vadghar (Ct), Panvel, Raigarh-410206

Office Phone: +91 22350 92125


Member details:
Member Name Designation
Harish Devji Gajora Partner
Dhawal Rameshbhai Patel Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Pralhad Keshav Patil Individual Area Share
Shridhar Keshav Patil Individual Area Share


Other Professionals involved:
Professional Name Professional Type
Atul Patel Architects and Associates Architect
B S Sukthankar and Associates Engineer
Rutuja Narsingh And Associates Chartered Accountant
SK Consultants & Engineers Engineer


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Om Nirman: A New Residential Development in Vadghar, Raigarh

Om Nirman, a new residential project registered under RERA ID P52000050931, is set to rise in the burgeoning locality of Pushpak-Vadghar, Vadghar (CT) in Raigarh district, Maharashtra. Developed by Nirman Infra, a partnership firm, the project offers a unique blend of modern living and affordability, making it an attractive proposition for homebuyers.

The project, located at Plot No-100, Sector No- R5, spans a total plot area of 319 sq mts. It comprises a single building with 7 sanctioned floors and a stilt, offering a total built-up area of 725 sq mts. The project has been meticulously designed with a focus on maximizing usable space, offering a variety of unit configurations to cater to diverse needs.

Units on Offer:

Om Nirman provides a choice of compact and efficient living spaces, with units ranging from 1RKs to 2BHKs. The project offers:

  • 11 units of 1BHKs ranging in size from 279 to 306 sq ft
  • 4 units of 1RKs measuring 197 sq ft
  • 2 units of 2BHKs spanning 623 sq ft

Amenities and Location:

While the project does not currently boast extensive recreational open space, it does offer basic amenities like parking. With 11 open parking spaces and 5 closed parking spaces, residents can rest assured of secure and convenient parking options. The project’s location in Sector No- R5 offers easy access to essential amenities like schools, hospitals, and markets, ensuring a comfortable lifestyle. The 9-meter wide road bordering the property provides convenient connectivity and facilitates smooth movement.

Project Timeline and Developer:

Om Nirman is expected to be completed by August 31st, 2026. The developer, Nirman Infra, is a partnership firm with a proven track record and a commitment to delivering quality projects. Their dedication to transparency and customer satisfaction is evident in the project’s RERA registration and the availability of contact information for inquiries.

Investment Opportunity:

Om Nirman presents an excellent investment opportunity for individuals seeking a well-planned residential development in a rapidly growing location. The project’s combination of affordability, well-designed units, and convenient location makes it an attractive proposition for both end-users and investors. With the project’s completion date approaching, this is an opportune time to secure your dream home or a promising investment.

Further Information:

For detailed information regarding the project, including unit specifications, pricing details, and payment plans, interested individuals are encouraged to contact Nirman Infra at 2235092125 or visit their office located at Plot No-100, Sector No- R5, Vadghar, Raigarh, Maharashtra.

New documents listed below were uploaded to the Documents section:

  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 28
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 65
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 38
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 8
1 Overall Percentage of Completion of the work done For the entire Building /Wing 58.9

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 20 Septic Tank

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26 3 2
1BHK 26.77 3 3
1BHK 27.11 4 4

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 16
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 56
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 36
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 6
1 Overall Percentage of Completion of the work done For the entire Building /Wing 56.4

 

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26 3 1
1BHK 26.77 3 1
1BHK 27.11 4 3
1BHK 28.43 1 1

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 2 Building Plan Approval / NA Order for plotted development
  • 2 Commencement Certificates / NA Order for plotted development

 

Building/Plot Details section updated for field(s) as below:

Field updated New value
Number of Sanctioned Floors 7
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) 11

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 100
1 Stilt Floor 50
1 X number of Slabs of Super Structure 87
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 4
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 45
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 15
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 3
1 Overall Percentage of Completion of the work done For the entire Building /Wing 50.4

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 10 Septic Tank

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [3]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]