2024-12-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2023-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Ulwa, Pushpak(New), Ulawe, Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
275,sec 25A

Boundaries:
PLOT NO 274
PLOT NO 302N 11 METER WIDE ROAD
WE
S
PLOT NO 276

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 309 sq.mt.
Sanctioned Built-up Area: 463 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 4
No. of Plinths: 1
No. of Stilts: 1
No. of Closed Parking: 5

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 246 to 304 sq ft 12 2
1RK 181 to 201 sq ft 4 0
Shop 78 to 118 sq ft 4 2
Project Developer:
PRANAY KANHA KOLI c/o KANHA KOLI
Organization Type: Individual

Address: 457, 0, Vitthal Mandir, Ulwa, Ulwa,Panvel, , Panvel, Raigarh-410206




Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
SACHIN KANHA KOLI Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
A M ITHKULLA & ASSOCIATES Chartered Accountant
SHEETAL ARTICTECTS Architect
AGHARAKAR CONSUTANTS ENGINEER PVT LTD Engineer


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Embark on a Modern Haven: Introducing Suman Residency

In the vibrant tapestry of Ulwa, Raigarh, a captivating real estate project emerges – Suman Residency, a sanctuary of modern living nestled amidst urban charm. This meticulously planned development promises to transform your residential dreams into a tangible reality.

With RERA ID P52000034135, Suman Residency is a project of unwavering integrity, adhering to the highest industry standards. As a new project, it stands poised to commence construction, promising completion within the stipulated timeline. The extended date of completion ensures ample time for meticulous execution and delivery of a flawless product.

Spanning a sprawling plot of 309 square meters, Suman Residency encompasses a single majestic building with four elegantly designed floors. The ground floor boasts five spacious closed parking spaces, providing secure and convenient parking for residents.

The project offers a diverse range of units tailored to meet the diverse needs of homebuyers. Twelve meticulously planned 1BHK units range from 246 to 304 square feet, offering ample space and comfort. Four cozy 1RK units, ranging from 181 to 201 square feet, provide an ideal starter home for individuals or small families. Additionally, four compact yet functional shops, ranging from 78 to 118 square feet, offer entrepreneurial opportunities within the community.

Located in the heart of Ulwa, Suman Residency enjoys seamless connectivity to major transportation hubs and key amenities. The proximity to pushing back (new) street ensures easy access to public transportation and local markets. The Pin Code 410206 further enhances the project’s accessibility and desirability.

The financial integrity of Suman Residency is assured by its trusted banking partner, GP Parsik Sahakari Bank Ltd. With a strong track record and unwavering commitment to customer satisfaction, the bank provides secure and efficient financial transactions.

Suman Residency is a project that prioritizes the well-being of its residents. The thoughtfully planned layout ensures ample natural light and ventilation, creating a serene and healthy living environment. The recreational open space, although not sanctioned, is an integral part of the project’s vision, offering residents a sanctuary for relaxation and rejuvenation.

Welcome to Suman Residency, where modern living seamlessly intertwines with urban convenience. Embrace the opportunity to make this architectural masterpiece your own, a testament to your discerning taste and aspirations.

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Landscaping & Tree Planting : 50 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : 25 WORK IN PROGRESS
Water Supply : 50 WORK IN PROGRESS

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Disclosure of sold/ booked inventory
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
1 Overall Percentage of Completion of the work done For the entire Building /Wing 79

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.23 3 2
Shop 10.96 1 1
Shop 7.32 1 1

 

Building/Plot Details section updated for field(s) as below:

Field updated New value
Number of Plinth 1
Number of Sanctioned Floors 4
Number of Stilts 1
Number of Closed Parking 5

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-12-30

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration about Commencement Certificate
  • 2 Declaration in FORM B
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 Stilt Floor 75
1 X number of Slabs of Super Structure 50
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 5 0 0

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Landscaping & Tree Planting : 25 Work in progress
Sewerage (Chamber, Lines, Septic Tank , STP) : 25 Work in progress

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances