Project Name: SHREE SIDDHI RESIDENCY
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-10-31
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2021-10-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Ulwe, Sector 19 Ulwe, Ulawe, Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 169

Boundaries:
PLOT NO 170
PLOT NO 181N 15 METER WIDE ROAD
WE
S
PLOT NO 168

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 549 sq.mt.
Sanctioned Built-up Area: 824 sq.mt.
Recreational Open Space: 549 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 8
No. of Plinths: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 152 to 315 sq ft 14 13
Others 152 to 315 sq ft 14 0
Shop 162 to 173 sq ft 4 0
Project Developer:
SHREE SAI HOMES BUILDERS AND DEVELOPERS
Organization Type: Partnership

Address: Shop No.14 & 15, Chaumeshwar Apartment, Plot No B 79, Sector 23, Seawoods Nerul Navi Mumbai, Navi Mumbai (M Corp.), Thane-400706

Office Phone: +91 22254 12547


Member details:
Member Name Designation
VANDANA VIJAYKUMAR MADNE Authorized Signatory
RACHANA SANDESH VAIVUDE Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
AVINASH DHAVJI NAIK Individual Revenue Share
ARUN DHAVJI NAIK Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
ATUL PATEL Architect
DEVYANI SHEJWAL Chartered Accountant
Sandesh Vaivude Engineer


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Unveiling Shree Siddhi Residency: A New Residential Haven in Ulwe, Navi Mumbai

Shree Siddhi Residency, a promising new residential project nestled in the burgeoning locality of Ulwe, Navi Mumbai, is now open for investment. Developed by Shree Sai Homes Builders and Developers, this project is designed to offer a contemporary living experience, encompassing a range of thoughtfully crafted residential units and commercial spaces.

Located in Sector 19 Ulwe, the project occupies a prime plot of land spanning 549 square meters. The strategic location offers easy access to key transportation networks and essential amenities, making it an ideal choice for those seeking a balanced lifestyle.

Shree Siddhi Residency boasts a unique design with a single building comprising 8 sanctioned floors, ensuring ample natural light and ventilation for each unit. The project offers a diverse range of options, including 1BHK apartments, thoughtfully designed Others units, and conveniently located shop spaces, catering to various needs and budgets.

The project’s design prioritizes the well-being of its residents, incorporating a total recreational open space of 549 square meters, providing ample opportunity for relaxation and social interaction. While the project is currently in its initial stages, with a proposed completion date of October 31st, 2023, Shree Sai Homes Builders and Developers are committed to delivering a high-quality and timely project.

Shree Siddhi Residency is registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under the ID P52000029213, ensuring transparency and accountability throughout the development process. With no reported litigations and a dedicated team of professionals, the project offers a secure and reliable investment opportunity.

This meticulously planned project in Ulwe, Navi Mumbai, is poised to become a desirable address, promising a comfortable and vibrant lifestyle for its residents. For further information on Shree Siddhi Residency and its available units, please contact Shree Sai Homes Builders and Developers at 2225412547.

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-10-31

 

New documents listed below were uploaded to the Documents section:

  • 2 a Details of encumbrances concerned to Finance
  • 1 b Details of encumbrances concerned to Legal
  • 1 Deviation Report with respect to Allotment letter
  • 1 Deviation Report with respect to model copy of Agreement

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Overall Percentage of Completion of the work done For the entire Building /Wing 90

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 14.17 2 1
1BHK 19.03 1 1
1BHK 20.81 1 1
1BHK 29.34 6 6
landowner 14.17 2 0
landowner 19.03 3 0
landowner 20.81 3 0
landowner 24.26 4 0
landowner 29.34 2 0
landowner shop 15.12 1 0
landowner shop 16.15 1 0
shop 15.12 1 0
shop 16.15 1 0

 

New documents listed below were uploaded to the Documents section:

  • 2 CERSAI details
  • 2 Disclosure of Interest in Other Real Estate Organizations

 

New documents listed below were uploaded to the Documents section:

  • 1 CERSAI details
  • 1 Disclosure of Interest in Other Real Estate Organizations

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 4 Disclosure of sold/ booked inventory
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration about Commencement Certificate
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Declaration in FORM B
  • 2 Disclosure of sold/ booked inventory
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Sandesh Vaivude Engineer

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 99
1 Overall Percentage of Completion of the work done For the entire Building /Wing 89.9

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 9 0 0

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 14.17 4 1
1BHK 29.34 8 6

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [5]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development [3]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Other – Finance
  • Other – Legal [3]
  • Proforma of Allotment letter [2]