RERA ID: P52000024057
Project Name: SHIVAM
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-08-27
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2023-08-28).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Sector 16, Roadpali, Rodpali, Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 53 SECTOR 16

Boundaries:
9 MTR WIDE TO THE NORTH
11 MTR WIDE ROAD TO THE WESTN PLOT NO 52 to the EAST
WE
S
PLOT NO 33 AND 34 TO THE SOUTH

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 799 sq.mt.
Sanctioned Built-up Area: 1198 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 0
No. of Stilts: 1
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 234 to 278 sq ft 49 29
Shop 98 to 204 sq ft 9 1
Project Developer:
HARESHKUMAR RASIKLAL SHAH c/o RASIKLAL SHAH
Organization Type: Individual

Address: Shop No 1 And 2, Parasmani Chsl, Plot No 18, Sector 09, Kamothe Panvel, Kamothe, Panvel, Raigarh-410209

Office Phone: +91 22289 92961


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
MOHAN ATMARAM POPETA Individual Revenue Share
MACHINDRA ATMARAM POPETA Individual Revenue Share
YASHWANT BALIRAM POPETA Individual Revenue Share
LAXMIBAI ATMARAM POPETA Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
Vijaykumar Manilal Patel Contractor
VILAS AGHARKAR Engineer
SHEETAL ARCHITECT Architect
JAYESH PATEL Chartered Accountant


Projects in the state by this developer:
P52000048151 - RUDRAKSHA - Raigarh
P52000024057 - SHIVAM - Raigarh
P52000016669 - RUDRA - Raigarh
P52000016188 - RAMDOOT - Raigarh
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Unveiling SHIVAM: A New Real Estate Opportunity in Rodpali, Maharashtra

SHIVAM, a new real estate project registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under ID P52000024057, presents a unique opportunity for investors and homebuyers seeking a promising investment in the rapidly developing region of Rodpali, Raigarh district. Located at PLOT NO 53 SECTOR 16, ROADPALI, the project is strategically positioned with easy access to key amenities and infrastructure.

Project Highlights:

  • New Project: SHIVAM is a brand new development, offering the advantage of modern design and construction techniques.
  • Completion Timeline: Projected for completion by August 28, 2024, SHIVAM promises timely delivery, assuring peace of mind for investors.
  • Strategic Location: Situated in Sector 16, Rodpali, the project benefits from its proximity to essential amenities and easy access to transportation networks.
  • Diverse Unit Options: SHIVAM offers a variety of unit types to cater to different needs and budgets, including 1BHK apartments ranging from 234 to 278 sq ft and shops with sizes ranging from 98 to 204 sq ft.
  • Promoter Involvement: The project includes a Promoter (Land Owner/ Investor) as defined by MahaRERA Order, ensuring transparency and accountability in project execution.
  • Sanctioned Plan: The project adheres to a sanctioned plan, ensuring compliance with all regulatory requirements and standards.

Amenities:

  • Stilts: The project incorporates 1 stilt, providing ample parking space and enhancing the aesthetics of the development.
  • Closed Parking: 1 closed parking space ensures secure parking facilities for residents and visitors.

Project Details:

  • Total Plot/Project Area: 799 sq mts
  • Total Number of Proposed Buildings/Wings: 1
  • Sanctioned Built-up Area: 1198 sq mts
  • Permissible Total FSI: 1198 sq mts
  • Bank: SVC COOPERATIVE
  • IFSC Code: SVCB0000036

Investment Opportunity:

SHIVAM presents an attractive investment opportunity with its strategic location, diverse unit options, and commitment to quality construction. The project’s timely completion timeline and the involvement of a Promoter (Land Owner/ Investor) further enhance investor confidence.

Call to Action:

For detailed information on SHIVAM, including pricing, unit specifications, and payment plans, please contact [Contact Information] or visit our website at [Website Address]. Don’t miss out on this chance to secure your piece of a thriving community in Rodpali!

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 21.75 5 2
1BHK 23.16 3 2
1BHK 24.33 2 1
1BHK 24.45 2 1
1BHK 24.85 1 1
1BHK 24.96 5 2
1BHK 25.07 5 2
1BHK 25.11 5 3
1BHK 25.16 1 1
1BHK 25.17 1 1
1BHK 25.28 5 2
1BHK 25.43 10 7
1BHK 25.46 1 1
1BHK 25.85 3 3
Shop 9.16 1 0
Shop 9.3 1 0
Shop 9.55 1 0
Shop 9.57 1 0
Shop 9.64 1 0
Shop 9.73 2 1
Shop 15.31 1 0
Shop 19.03 1 0

 

New documents listed below were uploaded to the Documents section:

  • 1 Deviation Report with respect to model copy of Agreement
  • 1 CERSAI details
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 1 Proforma of Agreement for sale
  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Deviation Report with respect to Allotment letter
  • 1 b Details of encumbrances concerned to Legal
  • 2 a Details of encumbrances concerned to Finance
  • 4 Declaration about Commencement Certificate

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Supply : 85 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : 90 WORK IN PROGRESS

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 92
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 92
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 93
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 86.2

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 23.15 3 2
1BHK 24.32 2 1
1BHK 24.44 2 1
1BHK 25.16 2 2
1BHK 25.28 4 4
1BHK 25.42 10 10
1BHK 25.46 2 1
1BHK 25.85 4 4

 

New documents listed below were uploaded to the Documents section:

  • 4 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 7 Building Plan Approval / NA Order for plotted development
  • 8 Building Plan Approval / NA Order for plotted development
  • 9 Building Plan Approval / NA Order for plotted development
  • 3 Commencement Certificates / NA Order for plotted development
  • 3 Declaration about Commencement Certificate
  • 6 Building Plan Approval / NA Order for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 23.16 2 1
1BHK 24.33 2 1
1BHK 24.45 2 1
1BHK 24.85 2 2

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Supply : 80 WORK IN PROGRESS

 

New documents listed below were uploaded to the Documents section:

  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 85

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [6]
  • Building Plan Approval / NA Order for plotted development [5]
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [3]
  • Copy of the legal title report
  • Declaration about Commencement Certificate [2]
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [6]
  • Proforma of Allotment letter [2]