P52000023137
RERA ID: P52000023137
Project Name: MARATHON NEXZONE DAFFODIL - 2
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-06-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Palaspe Phata, J N Pt Road, Kolkhe, Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
96,96/2,98/6/2/2.98/6

Boundaries:
MUMBAI URAN NATINOAL HIGHWAY NH 4B
NALLAN GUTNO 94 1
WE
S
NALLA

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 581 sq.mt.
Sanctioned Built-up Area: 700 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 13
No. of Closed Parking: 50

Units on Offer and Availability
Project Developer:
SANVO RESORTS PVT. LTD.
Organization Type: Company

Address: 702, Marathon Max, Mulund Goregoan Link Road Junction, Mulund West, Sonapur Junction, Kurla, Mumbai Suburban-400080

Office Phone: +91 22677 28484


Member details:
Member Name Designation
DWARKANATH KRISHNAMURTHY RAO Authorized Signatory
K S RAGHAVAN Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
MATRIX ARCHITECTS & ENGINEERS Architect
DINESH PAI & CO Chartered Accountant
IXOXI Construction LLP Contractor
GURRUNATH S DHAVANN Engineer
SANJEEV KUMAR Engineer


Projects in the state by this developer:
P52000029859 - MARATHON NEXZONE ASTER - 1 - Raigarh
P52000029858 - MARATHON NEXZONE BODHI - 1 - Raigarh
P52000029857 - MARATHON NEXZONE BODHI - 2 - Raigarh
P52000023255 - MARATHON NEXZONE CEDAR - 2 - Raigarh
P52000023254 - MARATHON NEXZONE DAFFODIL - 1 - Raigarh
P52000023250 - MARATHON NEXZONE CEDAR - 1 - Raigarh
P52000023228 - MARATHON NEXZONE PLAZA 2 - Raigarh
P52000023148 - MARATHON NEXZONE ASTER - 2 - Raigarh
P52000023137 - MARATHON NEXZONE DAFFODIL - 2 - Raigarh
P52000001062 - MARATHON NEXZONE ACRUX -2 - Raigarh
…and 23 more
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

A New Chapter in Coastal Living: Introducing Marathon Nexzone Daffodil - 2

Nestled in the scenic locale of Palaspe Phata, Raigarh, Maharashtra, Marathon Nexzone Daffodil - 2 emerges as a new residential project promising a tranquil lifestyle. This development, registered under RERA ID P52000023137, is poised to redefine coastal living with its modern design and strategically planned amenities.

The project, spanning a total area of 581 sq. meters, is situated on plot number 96, 96/2, 98/6/2/2.98/6. The site enjoys strategic positioning with access from the J N PT Road and is bordered by Gutno 94 on the east, a Nalla on the west and south, and the Mumbai Uran National Highway NH 4B on the north.

The developer, Sanvo Resorts Pvt. Ltd., a reputable company with offices in Mulund West, Mumbai, is committed to delivering a quality project. The proposed completion date for Marathon Nexzone Daffodil - 2 is June 30th, 2026, promising a timely delivery of this exciting new development.

The project encompasses a single building with a sanctioned FSI of 700, resulting in a total sanctioned built-up area of 8000 sq. meters. This project boasts a 13-storey structure offering a mix of 1 BHK and 2 BHK units, catering to varied lifestyle needs.

Marathon Nexzone Daffodil - 2 offers a total of 98 units, including 69 spacious 1 BHK units ranging from 420 to 458 sq. ft. and 29 comfortable 2 BHK units spanning 580 to 671 sq. ft. This thoughtfully designed project caters to a diverse range of buyers seeking both cozy and spacious living options.

The development is further enhanced by a closed parking facility accommodating up to 50 vehicles, ensuring the convenience and security of residents.

Marathon Nexzone Daffodil - 2 promises a blend of modern living and coastal serenity. With its prime location, well-planned units, and commitment to timely completion, this project presents an excellent opportunity for those seeking a comfortable and convenient lifestyle amidst the beauty of the Konkan region.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 35
1 Overall Percentage of Completion of the work done For the entire Building /Wing 36.5

 

New documents listed below were uploaded to the Documents section:

  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Other – Technical
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Solid Waste Management And Disposal : 90 WORK IN PROGRESS
Internal Roads & Footpaths : 75 WORK IN PROGRESS
Water Conservation, Rain water Harvesting : 60 WORK IN PROGRESS
Fire Protection And Fire Safety Requirements : 100 Done
Electrical Meter Room, Sub-Station, Receiving Station : 20 WORK IN PROGRESS
Water Supply : 80 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : 98 work in progress
Storm Water Drains : 90 WORK IN PROGRESS
Treatment And Disposal Of Sewage And Sullage Water : 90 WORK IN PROGRESS

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 39.02 10 4
1BHK 39.39 20 8
1BHK 42.64 39 13
2BHK 53.96 13 4
2BHK 54.84 13 6
2BHK 62.43 3 1

 

New documents listed below were uploaded to the Documents section:

  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 80 WORK IN PROGRESS
Treatment And Disposal Of Sewage And Sullage Water : 60 WORK IN PROGRESS
Fire Protection And Fire Safety Requirements : 20 WORK IN PROGRESS
Internal Roads & Footpaths : 50 WORK IN PROGRESS

 

New documents listed below were uploaded to the Documents section:

  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 27
1 Overall Percentage of Completion of the work done For the entire Building /Wing 27.8

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 39.02 10 4
1BHK 42.64 39 13
2BHK 53.96 13 4

 

New documents listed below were uploaded to the Documents section:

  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 8
1 Overall Percentage of Completion of the work done For the entire Building /Wing 25.9

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 39.02 10 5
1BHK 39.39 20 8
1BHK 42.64 39 12
2BHK 54.84 13 6
2BHK 62.43 3 1

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 80 work in progress

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [9]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration in FORM B
  • Details of encumbrances [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [9]
  • Proforma of Allotment letter