MH
Raigarh
P52000021641
RERA ID: P52000021641
Project Name: Samruddhi Complex
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2023-12-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2022-12-30).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Village -Valap, Raigad, Valap, Panvel, Raigarh-410208

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Gut No -152

Boundaries:
Gut No - 153 2
Gut No -154N Road
WE
S
Gut No - 155

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 9180 sq.mt.
Sanctioned Built-up Area: 9115 sq.mt.
Recreational Open Space: 950 sq.mt.
No. of Buildings sanctioned: 5
No. of Floors sanctioned: 25
No. of Plinths: 5
No. of Stilts: 5
No. of Closed Parking: 5

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 261 to 352 sq ft 176 170
2BHK 538 sq ft 5 5
Project Developer:
SAMRUDDHI BUILDCON
Organization Type: Partnership

Address: Room No -7 ,3Rd Floor, Nl -1-A,Bldg No -01, Sector -10, Nerul West, Nerul, Navi Mumbai (M Corp.), Thane-400706

Office Phone: +91 99870 76563


Member details:
Member Name Designation
Annappa Appa Masal Authorized Signatory
Housabai Annappa Masal Partner
Naval Kisan Mane Partner
Kisan Jagannath Mane Partner
Suresh Devram Chaudhari Partner


Other Professionals involved:
Professional Name Professional Type
Vastukalp Architect
SK Consultants & Engineers Engineer
Gaurav S Rajpal & Co Chartered Accountant
RERA Easy Other Professional


Projects in the state by this developer:
P51700053740 - SAMRUDDHI FLORA - Thane
P51700051140 - SAI SAMRUDDHI - Thane
P51600029128 - SIDDHIVINAYAK ANNEX - Nashik
P52000021641 - Samruddhi Complex - Raigarh
P52100004435 - SPARSH HEIGHTS - Pune
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Embarking on an Extraordinary Real Estate Journey: Introducing Samruddhi Complex

In the picturesque region of Maharashtra, amidst the rolling hills and lush greenery, emerges Samruddhi Complex, a residential masterpiece that promises to elevate your living experience. This state-of-the-art project, meticulously crafted by the esteemed SAMRUDDHI BUILDCON, stands poised to redefine the concept of urban living.

Bearing the RERA ID P52000021641 and classified as a New Project, Samruddhi Complex is set to reach completion in December 2022, with an extended deadline of December 2023. With no litigations clouding its path, this project proudly boasts a pristine legal standing.

Nestled in the heart of Panvel, Samruddhi Complex sprawls across an expansive 9180 square meters of prime land. Its strategic location amidst serene surroundings yet within easy reach of urban amenities offers the perfect balance of tranquility and convenience. The complex comprises five elegantly designed buildings, each towering over 25 stories, offering panoramic views of the surrounding landscape.

The project’s thoughtful amenities cater to the discerning needs of discerning homeowners. Five spacious stilts provide ample parking space, while the meticulously landscaped open spaces of 950 square meters invite residents to indulge in leisurely activities. The complex also boasts a host of modern conveniences, including closed parking, ensuring maximum comfort and security.

Samruddhi Complex offers a wide selection of unit configurations to suit every taste and lifestyle. From cozy 1BHK apartments ranging in size from 261 to 352 square feet to spacious 2BHK units measuring 538 square feet, there is an option to meet every family’s requirements. Each unit is designed with meticulous attention to detail, featuring airy balconies that flood the spaces with natural light and fresh air.

With its exceptional amenities, prime location, and commitment to quality construction, Samruddhi Complex is poised to become a landmark in Panvel. It is an investment not only in a home but in a lifestyle that is both aspirational and attainable. Whether you seek a tranquil retreat or a vibrant urban hub, Samruddhi Complex offers the perfect setting to embark on your next chapter.

New documents listed below were uploaded to the Documents section:

  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)

 

New documents listed below were uploaded to the Documents section:

  • 1 Status of Conveyance

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 100
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 100
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
3 Overall Percentage of Completion of the work done For the entire Building /Wing 100
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
4 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
4 Overall Percentage of Completion of the work done For the entire Building /Wing 100
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
5 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
5 Overall Percentage of Completion of the work done For the entire Building /Wing 100

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 24.26 5 5
1BHK 27.86 94 92
1BHK 32.73 77 73
2BHK 50.06 5 5

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 100 Completed
Water Conservation, Rain water Harvesting : 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 Completed
Storm Water Drains : 100 Completed
Street Lighting : 100 Completed
Landscaping & Tree Planting : 100 Completed
Water Supply : 100 Completed
Open Parking : 100 Completed
Aggregate area of recreational Open Space : 100 Completed

 

New documents listed below were uploaded to the Documents section:

  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.86 94 92
1BHK 32.73 77 73

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval (IOD) [6]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [10]
  • Proforma of Allotment letter