RERA ID: P52100053604
Project Name: 5 RaceCourse By Skyi Phase I
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Wanwadi, Canal Road, Haveli, Pune-411040

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CTS No 994/2 to 994/14+977/6+977/8

Boundaries:
Canal
NalaN CTS No 977 P
WE
S
CTS No 929

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 4423 sq.mt.
Sanctioned Built-up Area: 13765 sq.mt.
Recreational Open Space: 1703 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 26
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 84
No. of Closed Parking: 84

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 1196 to 1236 sq ft 27 24
4BHK 1468 sq ft 65 49
Others 81 to 189 sq ft 36 7
Project Developer:
Enerrgia Skyi Landmarks
Organization Type: Partnership

Address: 274 & Others, Skyi Songbirds, Four Season Road, Bhugaon, Pwc Club, Mulshi, Pune-412115

Office Phone: +91 20297 05175


Member details:
Member Name Designation
Sushant Mohan Jadhav Authorized Signatory
Amit Anil Jagtap Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Mr. Jayprakash Jagannath Girme Individual Revenue Share
Mr. Madhukar Shankarrao Tayade Individual Revenue Share
Mr. Manohar Shankarrao Tayade Individual Revenue Share
Smt. Vaidehi Dattatray Gaikwad Individual Revenue Share
Dr. Swati Jayawantrao Anapat Individual Revenue Share
Mr. Nandakumar Jagannath Girme Individual Revenue Share
Mr. Bhalchandra Shankarrao Tayade Individual Revenue Share
Mr. Bhagwat Tulshiram Wagh Individual Revenue Share
Mr. Maruti Krushnaji Shinde Individual Revenue Share
Mr. Vilas Shankarrao Raut Individual Revenue Share
Mr. Hemant Ramchandra Raskar Individual Revenue Share
Mr. Govind Laxman Jadhav Individual Revenue Share
Mr. Pandurang Laxman Jadhav Individual Revenue Share
Mr. Pandharinath Laxman Jadhav Individual Revenue Share
Mr. Digambar Govind Jadhav Individual Revenue Share
Mr. Pravin Govind Jadhav Individual Revenue Share
Smt. Anjanabai Narayan Badhe Individual Revenue Share
Smt. Subhadra Shankar Korde Individual Revenue Share
Smt. Venubai Baburao Raskar Individual Revenue Share
Smt. Kamal Vasantrao Borawake Individual Revenue Share
Mr. Deepak Jagannath Girme Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
ANA Consortium Pvt Ltd Architect
Sandeep Rangdal & Asso Engineer
R V Porwal & Associates Chartered Accountant
Ar Dhananjay S Deshmukh Architect


Projects in the state by this developer:
P52100053604 - 5 RaceCourse By Skyi Phase I - Pune
P52100052969 - Skyi Iris, RaceCourse Phase I - Pune
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

A New Pinnacle of Urban Living: Introducing 5 RaceCourse By Skyi Phase I

Nestled in the heart of Wanwadi, Pune, 5 RaceCourse By Skyi Phase I is a brand-new residential project poised to redefine urban living. Developed by Enerrgia Skyi Landmarks, this project promises a blend of modern architecture, luxurious amenities, and a strategic location, making it an ideal choice for discerning homebuyers.

Registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under ID P52100053604, this project stands on a sprawling plot of 4423 sq. mtrs. (CTS No 994/2 to 994/14+977/6+977/8) and comprises a single building rising to an impressive 26 floors, offering a selection of exquisitely designed residences.

The project’s strategic location on Canal Road, Wanwadi (Pin code: 411040) provides easy access to the city’s key amenities and attractions. Situated amidst a serene environment, the project enjoys proximity to vital hubs like the Canal and Nala, offering a tranquil escape from the urban buzz.

5 RaceCourse By Skyi Phase I is more than just a residential project; it is a complete lifestyle experience. The project boasts an impressive range of amenities including:

  • Generous Recreational Open Space: The project dedicates 1703 sq. mtrs. to recreational areas, ensuring ample space for residents to unwind and connect.
  • Ample Parking: With 84 open parking and 84 closed parking spaces, residents can rest assured knowing their vehicles are secure.
  • Modern Design and Construction: The project’s single building rises to 26 floors, showcasing a contemporary architectural style and high-quality construction.

The project’s proposed date of completion is December 31st, 2027. This provides ample time for potential buyers to secure their dream homes and be a part of this exciting new venture.

Enerrgia Skyi Landmarks, with their proven track record in the real estate sector, brings their expertise to this project. Their commitment to quality, innovation, and customer satisfaction is reflected in every aspect of 5 RaceCourse By Skyi Phase I.

With its prime location, luxurious amenities, and developer’s reputation, 5 RaceCourse By Skyi Phase I promises a lifestyle of comfort, convenience, and unparalleled quality. This project is poised to become a coveted address, offering residents a truly unique and enriching living experience.

New documents listed below were uploaded to the Documents section:

  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 Stilt Floor 33
1 Overall Percentage of Completion of the work done For the entire Building /Wing 23.3

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 111.16 23 20
4BHK 136.42 65 49
Servant Room 10.62 2 1
Servant Room 14.09 2 1

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 13
1 Overall Percentage of Completion of the work done For the entire Building /Wing 11.3

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Temporary Infrastructure Sales office Sample flat : 98 as per consultant drawing
Internal Roads & Footpaths : 10 as per consultant drawing

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 111.16 23 21
4BHK 136.42 65 46
POD 17.58 2 1
Servant Room 10.06 2 1
Servant Room 10.26 2 1
Servant Room 10.42 2 1

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 111.16 23 19
3BHK 114.9 4 4
4BHK 136.42 65 44
POD 10.77 2 0
POD 10.78 2 0
POD 10.8 2 0
POD 11.17 2 0
POD 13.12 2 0
POD 15.94 2 0
POD 17.58 2 0
POD 7.55 2 0
POD 7.65 2 0
Servant Room 10.01 2 0
Servant Room 10.06 2 0
Servant Room 10.16 2 0
Servant Room 10.26 2 0
Servant Room 10.42 2 0
Servant Room 10.48 2 0
Servant Room 10.62 2 0
Servant Room 14.09 2 0
Servant Room 16.19 2 1

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Ar Dhananjay S Deshmukh Architect

 

New documents listed below were uploaded to the Documents section:

  • 3 Proforma of Agreement for sale
  • 2 Declaration about Commencement Certificate

 

New documents listed below were uploaded to the Documents section:

  • 1 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 111.16 23 19
3BHK 114.9 4 4
4BHK 136.42 65 44
Servant Room 16.19 2 1

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 15
1 Overall Percentage of Completion of the work done For the entire Building /Wing 11.5

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
POD 7.55 2 0
POD 7.65 2 0
POD 10.77 2 0
POD 10.78 2 0
POD 10.8 2 0
POD 11.17 2 0
POD 13.12 2 0
POD 15.94 2 0
POD 17.58 2 0
Servant Room 10.01 2 0
Servant Room 10.06 2 0
Servant Room 10.16 2 0
Servant Room 10.26 2 0
Servant Room 10.42 2 0
Servant Room 10.48 2 0
Servant Room 10.62 2 0
Servant Room 14.09 2 0
Servant Room 16.19 2 0

 

Number of Sanctioned Floors field under Building/Plot Details section updated with new value 26

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 111.16 23 9
3BHK 114.9 4 2
4BHK 136.42 65 23

 

New documents listed below were uploaded to the Documents section:

  • 14 Building Plan Approval / NA Order for plotted development
  • 13 Building Plan Approval / NA Order for plotted development
  • 12 Building Plan Approval / NA Order for plotted development
  • 15 Building Plan Approval / NA Order for plotted development
  • 16 Building Plan Approval / NA Order for plotted development
  • 17 Building Plan Approval / NA Order for plotted development
  • 18 Building Plan Approval / NA Order for plotted development
  • 2 CERSAI details
  • 2 Copy of Layout Approval (in case of layout)
  • 19 Building Plan Approval / NA Order for plotted development
  • 3 Commencement Certificates / NA Order for plotted development
  • 22 Building Plan Approval / NA Order for plotted development
  • 21 Building Plan Approval / NA Order for plotted development
  • 20 Building Plan Approval / NA Order for plotted development

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Temporary Infrastructure Sales office Sample flat : 95 as per consultant drawing
Internal Roads & Footpaths : 7 as per consultant drawing

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 106.64 19 2
3BHK 111.16 19 9
3BHK 114.9 3 2
4BHK 136.42 39 23

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 106.64 19 0
3BHK 111.16 19 0
3BHK 114.9 3 0
4BHK 136.42 39 0

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development [11]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Other – Legal
  • Other – Technical [2]
  • Proforma of Agreement for sale [2]
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]