MH
Pune
P52100029933
RERA ID: P52100029933
Project Name: Skyi Sula Heights Phase II
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-07-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Bhugaon, Paud Road, Mulshi, Pune-412115

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
451 Part and others

Boundaries:
Sr No 455
Sr No 451 453N Sr No 450 455
WE
S
Sr No 451

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3642 sq.mt.
Sanctioned Built-up Area: 5463 sq.mt.
Recreational Open Space: 1619 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 13
No. of Plinths: 1
No. of Podiums: 1
No. of Stilts: 1
No. of Open Parking: 20
No. of Closed Parking: 60

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 593 sq ft 4 4
3BHK 749 to 772 sq ft 77 72
Project Developer:
Enerrgia Skyi Developers
Organization Type: Partnership

Address: Sr No 77/2/16 Plot No 21, Sugat Residency, Bhusari Colony, Kothrud, Behind Ved Vihar, Haveli, Pune-411038

Office Phone: +91 20252 07279


Member details:
Member Name Designation
Sushant Mohan Jadhav Partner
Sushant Mohan Jadhav Authorized Signatory
Nitin Murlidhar Gaikwad Authorized Signatory


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Umesh Kisan Kandhare Individual Area Share
Ravindra Rajaram Kandhare Individual Area Share
Subhash Raghunath Jadhav Individual Area Share
Hemlata Dnyaneshwar Shinde Individual Area Share
Mahesh Sadanand Shetty Individual Area Share
Vijay Jagnnath Varule Individual Area Share


Other Professionals involved:
Professional Name Professional Type
ABS Architect and Associates Architect
Sandeep Rangdal and Associates Engineer
R V porwal and Associates Chartered Accountant
Ar Dhananjay S Deshmukh Architect
SPCM & Associates Chartered Accountant


Projects in the state by this developer:
P52100056325 - PWC Towers Hill Side Phase III - Pune
P52100029933 - Skyi Sula Heights Phase II - Pune
P52100028121 - Skyi Aria Heights Phase I - Pune
P52100019378 - Skyi Songbirds Commercial - Pune
P52100019348 - Skyi Songbirds Phase E - Pune
P52100001117 - Skyi Songbirds Phase B - Pune
P52100000805 - Skyi Songbirds Phase C - Pune
P52100000769 - Skyi Songbirds Phase A - Pune
P52100000764 - Skyi Songbirds Phase D - Pune
P52100000643 - The Songbirds Estate Phase I - Pune
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Skyi Sula Heights Phase II: A New Residential Project in Bhugaon, Pune

Skyi Sula Heights Phase II, a new residential project in Bhugaon, Pune, promises a luxurious and comfortable lifestyle amidst picturesque surroundings. Developed by Enerrgia Skyi Developers, this project is registered under MahaRERA with the ID P52100029933 and is expected to be completed by July 31st, 2025.

Located on Plot bearing number 451 Part and others, the project enjoys a strategic location in Bhugaon, Paud Road, Pune. Situated within a serene environment, Skyi Sula Heights Phase II provides easy access to essential amenities and infrastructure.

The project encompasses a total plot area of 3642 sqmts and features a single building with a total of 14 sanctioned floors, including a stilt floor. The project has been designed to incorporate a significant portion of open space, with 1619 sqmts dedicated to recreational amenities. Furthermore, the project includes a total of 80 parking slots, comprising 20 open parking spaces and 60 closed parking spaces.

Skyi Sula Heights Phase II boasts a well-planned layout with a focus on providing a comfortable and convenient living experience. The project will offer a range of amenities, designed to enhance the lifestyle of its residents.

Enerrgia Skyi Developers, a partnership firm with a proven track record in the real estate sector, is committed to delivering a high-quality project that meets the expectations of its residents. The firm is dedicated to transparency and accountability, evident in its adherence to MahaRERA regulations and its commitment to timely project completion.

With its strategic location, modern amenities, and experienced developer, Skyi Sula Heights Phase II presents an attractive opportunity for those seeking a comfortable and luxurious living experience in the serene surroundings of Bhugaon, Pune.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 64
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
1 Overall Percentage of Completion of the work done For the entire Building /Wing 58.4

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 69.63 27 26
3BHK 71.79 50 46

 

New documents listed below were uploaded to the Documents section:

  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 69.63 27 25
3BHK 71.79 50 44

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 55.12 4 4
3BHK 69.63 29 25
3BHK 71.79 54 44

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 90
Water Supply : 65 wtp shared facility with adjoining project

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

There are additions/modifications under Professionals section

Professional Name Professional Type
SPCM & Associates Chartered Accountant
Ar Dhananjay S Deshmukh Architect

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 42
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 43
1 Overall Percentage of Completion of the work done For the entire Building /Wing 61.4

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 35
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5

 

New documents listed below were uploaded to the Documents section:

  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 2 Disclosure of sold/ booked inventory
  • 2 Proforma of Agreement for sale
  • 3 Declaration about Commencement Certificate

 

New documents listed below were uploaded to the Documents section:

  • 4 Copy of the legal title report
  • 4 Copy of Layout Approval (in case of layout)
  • 5 Building Plan Approval / NA Order for plotted development
  • 6 Building Plan Approval / NA Order for plotted development
  • 3 Commencement Certificates / NA Order for plotted development

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 69.63 29 25
3BHK 71.79 54 41

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 70
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57

 

Number of Sanctioned Floors field under Building/Plot Details section updated with new value 14

 

New documents listed below were uploaded to the Documents section:

  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 69
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
1 Overall Percentage of Completion of the work done For the entire Building /Wing 56.9

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 69.63 27 25
3BHK 71.79 50 41

 

New documents listed below were uploaded to the Documents section:

  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 1 Deviation Report with respect to model copy of Agreement
  • 1 Disclosure of sold/ booked inventory

 

New documents listed below were uploaded to the Documents section:

  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [10]
  • Building Plan Approval / NA Order for plotted development [4]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [3]
  • Copy of the legal title report [3]
  • Declaration about Commencement Certificate [2]
  • Declaration in FORM B
  • Details of encumbrances [2]
  • Deviation Report with respect to Allotment letter
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [10]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal