2029-12-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Vadgaonsheri, Vadgaonsheri To Kalyaninagar Road, Haveli, Pune-411014

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
7/1,7/2,7/3,7/4,7/5, 8/1/1/2, 38A/1B/1, 3/2

Boundaries:
By 5th Phase
By 24 meter wide DP RoadN By Proposed Development of Building of 6th Phase
WE
S
By proposed development of building of 6th Phase

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 89 sq.mt.
Sanctioned Built-up Area: 1392 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 3
No. of basements: 5
No. of Closed Parking: 39

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Shop 154 to 497 sq ft 39 8
Project Developer:
Bramhacorp Limited
Organization Type: Company

Address: S. No. 12A, Plot No. 99, Corporate Office, Rbm Road, Sangamwadi, Next To Sheraton Grand, Pune (M Corp.), Pune City, Pune-411001

Office Phone: +91 20414 23333


Member details:
Member Name Designation
ALKA REGE Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Arpee Infra Corporation Contractor
Pamkajkumar Somvanshi Engineer
Faiz Shaikh & Co Chartered Accountant
FOURTH DIMENSION ARCHITECT PVT LTD Architect
SACHIN SHAH Architect


Projects in the state by this developer:
P52100054423 - BOULEVARD WING B 1 - Pune
P52100054406 - BRAMHACORP TOWNHOUSE A - Pune
P52100052374 - THE COLLECTION - W5 AND W6 - Pune
P52100051975 - BOULEVARD TOWER A2 - Pune
P52100051537 - HUES OF SKY - Pune
P52100048195 - AUGUST TOWERS PH 1 - Pune
P52100045518 - BRAMHACORP TOWNHOUSE A1 - Pune
P52100032719 - The Collection Premium - Pune
P52100028754 - The Collection - W2 and W7 - Pune
P52100025256 - BramhaCorp Smart - Pune
…and 12 more
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

The Collection - Commercial W1: A Prime Commercial Opportunity in Vadgaonsheri, Pune

The Collection - Commercial W1, a new commercial project by Bramhacorp Limited, presents an exciting investment opportunity in the vibrant locality of Vadgaonsheri, Pune. Located on a prime plot spanning 89 sq. mts., this project offers a strategic blend of accessibility, modern design, and lucrative commercial potential.

Strategic Location and Connectivity:

Situated on Vadgaonsheri to Kalyaninagar Road, The Collection - Commercial W1 enjoys excellent connectivity to key areas of Pune. The 24-meter wide DP Road provides easy access, while the proximity to the 5th and 6th phases of the development ensures a thriving commercial environment. This prime location offers easy accessibility to a diverse range of businesses, making it an ideal choice for both established and aspiring entrepreneurs.

Modern Architecture and Amenities:

The project boasts a thoughtfully designed building, rising to 3 floors above 5 basement levels. The modern architecture and amenities cater to the needs of a dynamic commercial environment. The 39 closed parking spaces provide ample parking for customers and employees, while the carefully planned layout ensures a seamless flow of foot traffic and efficient operation.

Investment Opportunity in a Thriving Locality:

Vadgaonsheri, known for its strong residential and commercial growth, offers a lucrative investment environment. The Collection - Commercial W1 provides a range of shop spaces, ranging from 154 to 497 sq ft, designed to cater to various commercial needs. With its strategic location, modern amenities, and growing demand, The Collection - Commercial W1 promises attractive returns on investment for discerning buyers.

RERA Compliance and Project Details:

The Collection - Commercial W1 is registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) with the RERA ID P52100022048. This ensures transparency and compliance with the necessary regulations. The project is scheduled for completion by December 30, 2029, with a total sanctioned FSI of 1392.

Bramhacorp Limited: A Trusted Developer:

Bramhacorp Limited, known for its commitment to quality and timely delivery, brings its expertise to The Collection - Commercial W1. With a strong track record in the real estate industry, Bramhacorp Limited guarantees a reliable and rewarding investment experience.

Conclusion:

The Collection - Commercial W1 in Vadgaonsheri, Pune, offers an exceptional opportunity for those seeking a prime commercial space with excellent connectivity and future growth potential. This project, backed by the expertise of Bramhacorp Limited, presents an attractive investment proposition in a rapidly developing area of Pune.

New documents listed below were uploaded to the Documents section:

  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Shop 28.14 3 1
Shop 28.24 3 1
Shop 29.73 3 1
Shop 30.5 10 1

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Energy management : 95 -
Fire Protection And Fire Safety Requirements : 80 Fire fighting System
Electrical Meter Room, Sub-Station, Receiving Station : 95 Power Supply from MSEDCL
Water Supply : 60 Potable water supply from municipal corporation
Sewerage (Chamber, Lines, Septic Tank , STP) : 95 STP
Storm Water Drains : 85 Storm water drains
Street Lighting : 20 Electrical poles & lights
Landscaping & Tree Planting : 20 Trees and Plants
Water Conservation, Rain water Harvesting : 40 Rain water harvesting
Internal Roads & Footpaths : 70 Concrete Road
Treatment And Disposal Of Sewage And Sullage Water : 25 STP

 

New documents listed below were uploaded to the Documents section:

  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 20
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
1 Overall Percentage of Completion of the work done For the entire Building /Wing 70

 

A correction has been made to the Developer’s address. The complete address is now: S. No. 12A, Plot No. 99, Corporate Office, Rbm Road, Sangamwadi, Next To Sheraton Grand, Pune (M Corp.), Pune City, Pune-411001

 

New documents listed below were uploaded to the Documents section:

  • 2 Copy of Layout Approval (in case of layout)

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 13 Disclosure of sold/ booked inventory
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 10 STP
Street Lighting : 10 Electrical poles & lights
Sewerage (Chamber, Lines, Septic Tank , STP) : 85 STP
Internal Roads & Footpaths : 60 Concrete Road
Fire Protection And Fire Safety Requirements : 75 Fire fighting System
Electrical Meter Room, Sub-Station, Receiving Station : 90 Power Supply from MSEDCL
Water Supply : 40 Potable water supply from municipal corporation
Storm Water Drains : 75 Storm water drains

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Shop 14.37 2 0
Shop 28.14 3 1
Shop 28.24 3 1
Shop 29.73 3 1
Shop 30.21 6 2
Shop 30.29 3 1
Shop 30.5 10 0
Shop 30.51 3 1
Shop 31.56 3 0
Shop 46.23 3 0

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 65.4

 

New documents listed below were uploaded to the Documents section:

  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 12 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) [2]
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [14]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B [3]
  • Details of encumbrances [2]
  • Disclosure of sold/ booked inventory [11]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [7]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) [3]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [10]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter [2]