MH
Pune
P52100004692
RERA ID: P52100004692
Project Name: Riverdale Residences-I
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2023-10-30
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2022-10-30, 2021-10-31).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Kharadi, Shivane Road, Haveli, Pune-411014

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
16-1, 17-5

Boundaries:
Sr No 16-2 Part And 17-1 Part
Sr No 17-6 PartN River
WE
S
Sr No 17-6 Part And Sr No 18 Part

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 12451 sq.mt.
Sanctioned Built-up Area: 25668 sq.mt.
Recreational Open Space: 1345 sq.mt.
No. of Buildings sanctioned: 3
No. of Floors sanctioned: 69
No. of Plinths: 3
No. of Podiums: 12
No. of Stilts: 3
No. of Open Parking: 30
No. of Closed Parking: 552

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 1060 to 3236 sq ft 284 284
Project Developer:
Duville Estates Private Limited
Organization Type: Company

Address: 81, Sopan Baug, Race Course Road, Ghorpadi, Next To Midtown May Flower Society, Pune (M Corp.), Pune City, Pune-411001

Office Phone: +91 22226 10021


Member details:
Member Name Designation
Tushad Behram Dubash Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Pinnac AECL Consultancy Pvt Ltd Architect
JW Consultants LLP Engineer


Projects in the state by this developer:
P52100032106 - 30 DRIVE - Pune
P52100029023 - Riverdale Grove - Pune
P52100020853 - PLOT A BUILDING - Pune
P52100014163 - Riverdale Suites - Pune
P52100008035 - Riverdale Heights - Pune
P52100004692 - Riverdale Residences-I - Pune
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
Court of Civil Judge Senior Division Pune 1774 Civil Suit 2015 Dismissed by Honble District and Sessions Court Pune
Court of Civil Judge Senior Division Pune 226 Civil Suit 2015 Pending
Court of Civil Judge Senior Division Pune 597 Civil Suit 2015 Pending
Sub Divisional Officer Pune 221 Civil Appeal 2014 DISMISSED
Complaints

Complaint No Complainant Name
CC005000000208237 Abhinav Gupta
CC005000000208240 SAMIR KIRANRAO DHOK
CC005000000228462 KAVITA GOBIND AIDASANI
CC005000000238558 Akshay Mehta
CC005000000085632 Duville estates through authorised signatory Shrinivas Kulkarni
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Riverdale Residences-I: A Residential Haven in the Heart of Kharadi

Riverdale Residences-I, a sprawling residential project developed by Duville Estates Private Limited, promises a luxurious and comfortable living experience in the sought-after location of Kharadi, Pune. Registered under the Maharashtra Real Estate Regulatory Authority (MahaRERA) with ID P52100004692, this project offers a unique blend of modern architecture, meticulously crafted amenities, and a strategic location, making it an attractive proposition for discerning homebuyers.

Situated on a sprawling plot encompassing 12451 sq mtrs, Riverdale Residences-I boasts three meticulously designed buildings, each rising to a height of 69 floors, offering stunning views of the surrounding landscape. The project has been approved for a sanctioned FSI of 25668, allowing for a substantial built-up area of 284 units, including spacious 3BHK apartments ranging from 1060 to 3236 sq ft.

The project’s strategic location in Kharadi offers easy access to key amenities, with the bustling Shivaji Road running along its eastern boundary. The presence of a river adds to the serene and picturesque environment, providing a tranquil escape from the city’s hustle and bustle. While the project currently faces legal challenges, it holds immense potential for those seeking a sophisticated and convenient lifestyle in Pune.

Riverdale Residences-I prioritizes the well-being of its residents with an array of thoughtfully designed amenities. The project features a dedicated recreational open space of 1345 sq mtrs, offering ample opportunities for relaxation and recreation. Additionally, the project provides 30 open parking spaces and 552 closed parking spaces, catering to the parking needs of residents.

Duville Estates Private Limited, the developer, is known for its commitment to quality and timely delivery. However, it is important to note that the project has experienced delays, with the initial proposed date of completion being 2021-10-31, which was later revised to 2022-10-30 and finally extended to 2023-10-30. Potential buyers should carefully review the project’s status and legal intricacies before making any investment decisions.

Despite the current legal challenges and project delays, Riverdale Residences-I presents an opportunity to own a luxurious home in a prime location. With its spacious apartments, comprehensive amenities, and strategic location, this project holds the potential to become a landmark residential development in Kharadi.

There are modifications under Cases section

Court Name Case Number Case Type Petition Name Year Present Status
Court of Civil Judge Senior Division Pune 1774 Civil Suit 2015 Dismissed by Honble District and Sessions Court Pune

 

New complaints added under Complaints section

Complaint No Complainant Name
CC005000000085632 Duville estates through authorised signatory Shrinivas Kulkarni

 

New documents listed below were uploaded to the Documents section:

  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 10 Engineers Certificate on Quality Assurance (Form 2A)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Street Lighting : 100 WORK IN PROGRESS

 

New documents listed below were uploaded to the Documents section:

  • 10 Disclosure of sold/ booked inventory

 

New documents listed below were uploaded to the Documents section:

  • 3 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 100 WORK COMPLETED
Water Conservation, Rain water Harvesting : 100 WORK COMPLETED
Fire Protection And Fire Safety Requirements : 100 WORK COMPLETED
Electrical Meter Room, Sub-Station, Receiving Station : 100 WORK COMPLETED
Water Supply : 100 WORK COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 WORK COMPLETED
Storm Water Drains : 100 WORK COMPLETED
Landscaping & Tree Planting : 100 WORK COMPLETED
Street Lighting : 95 WORK IN PROGRESS
Treatment And Disposal Of Sewage And Sullage Water : 100 WORK COMPLETED
Solid Waste Management And Disposal : 100 WORK COMPLETED

 

New documents listed below were uploaded to the Documents section:

  • 9 Disclosure of sold/ booked inventory
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK Odd River F 111.39 22 21

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 0
1 X number of Podiums 100
1 Stilt Floor 0
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 80
2 X number of Basement(s) and Plinth 0
2 Stilt Floor 0
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 80
3 X number of Basement(s) and Plinth 0
3 Stilt Floor 0
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
3 Overall Percentage of Completion of the work done For the entire Building /Wing 80

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3 BHK RF Even 111.76 24 24
3BHK Even Podium F 133.8 1 1
3BHK Even River F 111.76 22 22
3BHK Even River F 188.09 1 1
3BHK Even River F 300.71 1 1
3BHK Odd River F 111.39 22 22
3BHK PF Garden O 115.66 2 2
3BHK Podium F 168.1 1 1
3BHK River Facing O 111.39 22 22

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) [2]
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval (IOD) [2]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [10]
  • Certificates of CA (Form 5) [2]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [9]
  • Commencement Certificates / NA Order for plotted development [5]
  • Copy of Layout Approval (in case of layout) [4]
  • Copy of the legal title report [4]
  • Declaration about Commencement Certificate
  • Declaration in FORM B [9]
  • Details of encumbrances [7]
  • Disclosure of sold/ booked inventory [8]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A) [9]
  • Other [13]
  • Proforma of Allotment letter [3]
  • Status of Formation of Legal Entity (Society/Co Op etc.)