MH
Pune
P52100002998
RERA ID: P52100002998
Project Name: Aapla Ghar Moshi Annex Phase I
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2027-12-31
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2023-12-30, 2022-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
, Kharabwadi (Ct), Khed, Pune-410501

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
184 and others

Boundaries:
Adjacent Plot A and B
emaining part of 184 and others and RP roadN Ramaning Part of Gat No 184 and Others
WE
S
Internal Road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 4822 sq.mt.
Sanctioned Built-up Area: 9614 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 20
No. of Plinths: 2
No. of Stilts: 2
No. of Closed Parking: 35

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 234 to 285 sq ft 216 122
2BHK 426 to 490 sq ft 60 28
Shop 68 to 101 sq ft 20 20
Project Developer:
Maple Shelters Pvt. Ltd.
Organization Type: Company

Address: 702 7Th Floor, City Square, University Road, Shivajinagar, Behind The Pride Hotel, Pune (M Corp.), Pune City, Pune-411005

Office Phone: +91 20490 11111
Website URL: www.mapleshelters.com


Member details:
Member Name Designation
Sachin Ashok Agarwal Managing Director
Navin Ashok Agarwal Authorized Signatory


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Anish Sanjay Ruikar Individual Revenue Share
ADM and Company Partnership Revenue Share


Other Professionals involved:
Professional Name Professional Type
Jay aeram Architectural and interior consultant Architect


Litigations

Litigations related to the project ? No
Complaints

Complaint No Complainant Name
CC005000000022856 Maple Shelters Pvt Ltd Through its Director Sachin A Agarwal
CC005000000022991 Maple Shelters Pvt Ltd through its Director Sachin Ashok Agarwal
CC005000000022992 Maple Shelters Pvt Ltd through its Director Sachin A Agarwal
CC005000000085536 Maple Shelters Pvt Ltd Through its Partner Mr. Sachin Ashok Agarwal
CC005000000085660 Maple Shelters Pvt Ltd Through its Director Mr. Sachin Ashok Agarwal
CC005000000033605 PAYAL DEVDATTA POKHARKAR
CC005000000033605 PARAG PRAKASH MANJARE
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Aapla Ghar Moshi Annex Phase I: A New Home in the Heart of Pune

Aapla Ghar Moshi Annex Phase I, a residential project by Maple Shelters Pvt. Ltd., promises to redefine comfortable living in the bustling city of Pune. Situated in Kharabwadi (CT), Taluka Khed, the project offers a unique blend of modern amenities and convenient location, making it an ideal choice for families and individuals alike.

This on-going project, registered under RERA ID P52100002998, is designed to cater to diverse needs with a range of unit options. The project offers 1BHK units ranging from 234 to 285 square feet, 2BHK units from 426 to 490 square feet, and commercial shops ranging from 68 to 101 square feet, ensuring a suitable dwelling for every requirement.

Spanning across a total plot area of 4822 square meters, the project boasts two buildings, each rising to a height of 20 floors. With a sanctioned FSI of 9614, the project provides a generous built-up area, ensuring ample space and comfortable living.

The project strategically utilizes its space, including two stilt floors for parking, accommodating 35 closed parking spaces. While there is no dedicated recreational open space as per the sanctioned plan, the project’s location offers easy access to nearby parks and green spaces, providing residents with opportunities for relaxation and recreation.

Maple Shelters Pvt. Ltd., a well-established company with a strong track record, is committed to delivering a high-quality project. The project’s location, just off RP road and bordered by adjacent plots A and B, offers convenient access to key areas of the city. The project’s proximity to essential amenities, including shopping centers, schools, and hospitals, further enhances its appeal.

The initial proposed date of completion was December 31st, 2022, which was later revised to December 30th, 2023. While the project is currently undergoing construction, the extended completion date has been set to December 31st, 2027.

Aapla Ghar Moshi Annex Phase I presents a unique opportunity for those seeking a comfortable and modern home in a prime location within Pune. The project’s commitment to quality construction and its convenient location make it a compelling choice for those looking to invest in their future.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 X number of Slabs of Super Structure 67
2 Overall Percentage of Completion of the work done For the entire Building /Wing 42.2

 

New documents listed below were uploaded to the Documents section:

  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 4 Disclosure of sold/ booked inventory
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 21.74 124 62
1BHK 22.85 28 1
1BHK 25.14 24 22

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 0 STP After project completion inc. future developme
Landscaping & Tree Planting : 25 After project completion inc. future Development

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Community Buildings : 80 Club House After the project Completion inc. futur

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 21.74 124 61
1BHK 22.85 28 0
2BHK 39.58 44 13
Shop 6.62 6 6
Shop 6.92 6 6

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 X number of Slabs of Super Structure 58
2 Overall Percentage of Completion of the work done For the entire Building /Wing 41.3

 

New documents listed below were uploaded to the Documents section:

  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 19.5 10 4
1BHK 23.64 24 23
1BHK 25.14 24 20
2BHK 38.4 11 2
2BHK 41.87 8 8

 

New documents listed below were uploaded to the Documents section:

  • 2 Building Plan Approval (IOD)
  • 3 Building Plan Approval (IOD)

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2027-12-31

 

New documents listed below were uploaded to the Documents section:

  • 3 Declaration in FORM B
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 X number of Slabs of Super Structure 54
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 35
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 25
2 Overall Percentage of Completion of the work done For the entire Building /Wing 40.9

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Electrical Meter Room, Sub-Station, Receiving Station : 50 After project completion inc. future Development
Street Lighting : 15 After the building completion
Community Buildings : 25 Club House After the project Completion inc. futur

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 35 0 50

 

New documents listed below were uploaded to the Documents section:

  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 2 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 23.64 24 22
1BHK 24.66 8 8

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) [2]
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23) [2]
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [5]
  • Certificates of CA (Form 5) [3]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [6]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [4]
  • Declaration about Commencement Certificate [2]
  • Declaration in FORM B [2]
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) [3]
  • Form 2A [2]
  • Other
  • Proforma of Allotment letter [2]