MH
Mumbai Suburban
P51800045342
RERA ID: P51800045342
Project Name: ARKADE CROWN
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-12-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Eksar, Svp Road, Borivali, Mumbai Suburban-400103

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CTS No. 1430

Boundaries:
Pluto Society
Nirmal Sagar ApartmentN SVP Road
WE
S
Ami Prabha and Chandra Society

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 5711 sq.mt.
Sanctioned Built-up Area: 16696 sq.mt.
Recreational Open Space: 2518 sq.mt.
No. of Buildings sanctioned: 3
No. of Floors sanctioned: 57
No. of Plinths: 3
No. of Podiums: 12
No. of Stilts: 3

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 399 to 468 sq ft 48 42
1RK 223 sq ft 1 1
2BHK 511 to 720 sq ft 109 106
3BHK 835 to 1152 sq ft 64 55
4BHK 1288 sq ft 14 13
Project Developer:
Arkade Developers Private Limited
Organization Type: Company

Address: 2Nd Floor, Arkade House, Atmaram Sawant Marg, Ashok Nagar, Kandivali East, Next To Children’S Academy School, Borivali, Mumbai Suburban-400101

Office Phone: +91 22288 74742
Website URL: arkade.in


Member details:
Member Name Designation
Sandeep Ummedmal Jain Director
Arpit Vikram Jain Director
Amit Mangilal jain Authorized Signatory
Arpit Vikram Jain Authorized Signatory
Sandeep Ummedmal Jain Authorized Signatory
Amit Mangilal Jain Director


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Vithal Mandir CHSL Societies Area Share


Other Professionals involved:
Professional Name Professional Type
Kalakruti Architects & planners Architect
Jignesh Mohan Patel Engineer
Amit T jain & Co Chartered Accountant
Santosh B Morge & Co Chartered Accountant


Projects in the state by this developer:
P51800045342 - ARKADE CROWN - Mumbai Suburban
P51800034603 - Arkade Aspire - Mumbai Suburban
P51800029961 - Arkade Serene - Mumbai Suburban
P51800027271 - DARSHAN - Mumbai Suburban
P51800022666 - ARKADE EARTH - HAZEL - Mumbai Suburban
P51800014422 - ARKADE EARTH-CARNATION - Mumbai Suburban
P51800011586 - ARKADE EARTH- BLUEBELL - Mumbai Suburban
P51800010074 - ARKADE EARTH - GARDENIA - Mumbai Suburban
P51800008953 - ARKADE EARTH - EBONY - Mumbai Suburban
P51800006579 - ARKADE EARTH-ASPEN - Mumbai Suburban
…and 2 more
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

ARKADE CROWN: A New Residential Landmark in Eksar, Borivali

ARKADE CROWN, a new residential project by Arkade Developers Private Limited, is set to redefine luxury living in the coveted locality of Eksar, Borivali. This project, registered with RERA ID P51800045342, promises a modern and comfortable lifestyle with its thoughtfully designed apartments and an array of amenities.

Located at CTS No. 1430, ARKADE CROWN boasts a prime location on SVP Road, surrounded by established residential societies like Nirmal Sagar Apartment, Pluto Society, Ami Prabha, and Chandra Society. This strategic location offers residents easy access to essential amenities and services while maintaining a peaceful and serene environment.

Spread across a total plot area of 5711 sq. meters, ARKADE CROWN comprises three buildings, each rising up to 57 floors with 3 stilts. The project features a generous recreational open space of 2518 sq. meters, providing ample room for relaxation and recreation.

The project is set to offer a diverse range of apartments catering to different needs and preferences:

  • 1BHK (399 to 468 sq ft) - 48 Nos
  • 1RK (223 sq ft) - 1 Nos
  • 2BHK (511 to 720 sq ft) - 109 Nos
  • 3BHK (835 to 1152 sq ft) - 64 Nos
  • 4BHK (1288 sq ft) - 14 Nos

ARKADE CROWN promises a lifestyle of convenience and luxury with a range of amenities designed to enhance residents’ well-being. While the specific amenities are not explicitly mentioned, the 12 podium levels and 3 plinth levels hint at a multi-faceted approach to recreational and social spaces.

With a proposed completion date of December 31st, 2025, and no reported litigations, ARKADE CROWN presents a promising opportunity for those seeking a well-planned and comfortable home in a sought-after location. Interested buyers can contact Arkade Developers Private Limited at 2228874742 or visit their website at arkade.in for further details and to explore this exciting new development.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 40.25 2 1
3BHK 98.84 11 4

 

New documents listed below were uploaded to the Documents section:

  • 1 Architect’s Certificate on Completion of Project (Form 4)

 

New documents listed below were uploaded to the Documents section:

  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 5 Details of encumbrances
  • 4 Details of encumbrances

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Santosh B Morge & Co Chartered Accountant

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 40.05 17 12
1BHK 42.43 12 12
1BHK 43.5 7 7
2BHK 55.28 10 10
2BHK 63.53 6 6
2BHK 66.87 16 15
3.5 and 4 BHK 119.74 14 13
3BHK 107.06 18 17

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 50
Landscaping & Tree Planting : 50
Water Conservation, Rain water Harvesting : 75
Energy management : 75
Fire Protection And Fire Safety Requirements : 75
Electrical Meter Room, Sub-Station, Receiving Station : 75
Fitness Centre Society Office : 50
Water Supply : 75
Storm Water Drains : 75
Street Lighting : 50

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 84
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 59
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 43
1 Overall Percentage of Completion of the work done For the entire Building /Wing 67.9
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 73
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 88
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 59
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
2 Overall Percentage of Completion of the work done For the entire Building /Wing 66
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 87
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 92
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 71
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 47
3 Overall Percentage of Completion of the work done For the entire Building /Wing 70.6

 

New documents listed below were uploaded to the Documents section:

  • 2 Commencement Certificates / NA Order for plotted development

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 70 Except Septic Tank
Solid Waste Management And Disposal : 70

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 37.1 2 2
1BHK 40.05 17 7
1BHK 42.43 12 11
2BHK 61 7 6
2BHK 63.06 6 6
2BHK 64.81 2 2
3.5 and 4 BHK 119.74 14 12
3BHK 107.06 18 15
3BHK 99.39 16 15

 

New documents listed below were uploaded to the Documents section:

  • 2 Disclosure of sold/ booked inventory
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 37
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 19
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 25
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 11
1 Overall Percentage of Completion of the work done For the entire Building /Wing 49.2
2 X number of Slabs of Super Structure 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 44
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 19
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 25
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 11
2 Overall Percentage of Completion of the work done For the entire Building /Wing 49.9
3 X number of Slabs of Super Structure 100
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 65
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 9
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 39
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 25
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
3 Overall Percentage of Completion of the work done For the entire Building /Wing 55.8

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [6]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [18]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances [3]
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Other
  • Proforma of Agreement for sale
  • Proforma of Allotment letter [2]