MH
Mumbai Suburban
P51800033514
RERA ID: P51800033514
Project Name: Runwal Avenue Wing - M
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-04-18
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2026-04-18).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Mulund, Village Kanjur, , Kurla, Mumbai Suburban-400042

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CTS No 1009/6 1013P 1014P 1014/1to6 1017 1017/1 to 6 1018/1 to 9 Village Kanjur Taluka Kurla Mulund

Boundaries:
Wing N - Bldg No 2
Wing L - Bldg No 2N Wing H -Bldg No 3
WE
S
Existing Nala

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 369 sq.mt.
Sanctioned Built-up Area: 15584 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 52
No. of Plinths: 1
No. of Podiums: 5
No. of Stilts: 1
No. of Closed Parking: 315

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 368 sq ft 91 17
2BHK 548 to 555 sq ft 84 33
3BHK 741 to 747 sq ft 42 19
Others 453 to 464 sq ft 92 77
Shop 76 to 715 sq ft 22 16
Project Developer:
Susneh Infrapark Private Limited
Organization Type: Company

Address: Aryabhatt Building, C G Compound, Kanjurmarg (East), Kanjurmarg, Kurla, Mumbai Suburban-400042

Office Phone: +91 22611 62000


Member details:
Member Name Designation
Lucy Roy Choudhary Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Sunil Ambre and Associate Architect
J W Consultant LLP Engineer
Kshirsagar and Associate Chartered Accountant


Projects in the state by this developer:
P51800048234 - Runwal Avenue Wing - I - Mumbai Suburban
P51800047714 - Runwal Avenue Wing - N - Mumbai Suburban
P51800033514 - Runwal Avenue Wing - M - Mumbai Suburban
P51800031895 - Runwal Avenue Wing - L - Mumbai Suburban
P51800028811 - Runwal Avenue Wing K - Mumbai Suburban
P51800026860 - Runwal Avenue Wing-J - Mumbai Suburban
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Runwal Avenue Wing - M: A New Residential Project in Mulund, Mumbai

Runwal Avenue Wing - M, a new residential project in the vibrant locality of Mulund, Mumbai, is poised to redefine urban living with its contemporary design and thoughtfully curated amenities. Developed by Susneh Infrapark Private Limited, this project is registered with MahaRERA under ID P51800033514, ensuring transparency and adherence to regulatory standards.

Situated in Kanjur Village, Mulund, the project encompasses a total plot area of 369 sq. meters, comprising a single building spread across 52 floors. The development boasts an impressive sanctioned FSI of 15584, which translates to a substantial built-up area, catering to a diverse range of housing needs.

Runwal Avenue Wing - M offers a comprehensive selection of residential units, including 1BHK, 2BHK, and 3BHK apartments, ranging from 368 sq. ft. to 747 sq. ft. In addition, there are 92 units classified as “Others,” encompassing areas between 453 sq. ft. and 464 sq. ft., and 22 commercial shop spaces, ranging from 76 sq. ft. to 715 sq. ft., making the project attractive for both residential and commercial purposes.

The project is designed to provide a comfortable and convenient living experience. Amenities include five podiums offering a variety of recreational and social spaces, ensuring residents have access to modern conveniences. The project also features 315 closed parking spaces, ensuring ample parking for residents and visitors.

Runwal Avenue Wing - M is strategically located in Mulund, a well-connected locality with excellent accessibility to public transportation and essential amenities. The project’s proximity to the Eastern Express Highway, the upcoming metro line, and other key infrastructure makes it an ideal choice for those seeking a well-connected and convenient lifestyle.

With its contemporary design, well-planned amenities, and strategic location, Runwal Avenue Wing - M promises to be a desirable addition to the Mulund landscape. The project is expected to be completed by April 18, 2026, and promises to offer a vibrant and fulfilling living experience for its residents.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1.5 BHK 42.17 43 36
1BHK 34.22 91 17
2BHK 51 42 5
3BHK plus Deck 69.48 23 15

 

New documents listed below were uploaded to the Documents section:

  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 9 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 80
1 X number of Slabs of Super Structure 19
1 Overall Percentage of Completion of the work done For the entire Building /Wing 33.9

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 315 155 0

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2027-04-18

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration in FORM B
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 25
1 Stilt Floor 0
1 X number of Slabs of Super Structure 0
1 Overall Percentage of Completion of the work done For the entire Building /Wing 22.5

 

New documents listed below were uploaded to the Documents section:

  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 95
1 X number of Slabs of Super Structure 15
1 Overall Percentage of Completion of the work done For the entire Building /Wing 41

 

New documents listed below were uploaded to the Documents section:

  • 8 Disclosure of sold/ booked inventory
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Other – Technical

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 315 153 0

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1.5 BHK 43.14 49 41
2BHK 51.64 42 29
3BHK plus Deck 69.48 23 16

 

New documents listed below were uploaded to the Documents section:

  • 40 Building Plan Approval / NA Order for plotted development
  • 41 Building Plan Approval / NA Order for plotted development
  • 42 Building Plan Approval / NA Order for plotted development
  • 43 Building Plan Approval / NA Order for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 4 Commencement Certificates / NA Order for plotted development

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 80
1 X number of Slabs of Super Structure 10
1 Overall Percentage of Completion of the work done For the entire Building /Wing 39

 

New documents listed below were uploaded to the Documents section:

  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Proforma of Agreement for sale

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1.5 BHK 42.17 43 34
1.5 BHK 43.14 49 40
2BHK 51.64 42 28
3BHK 68.86 19 5
3BHK plus Deck 69.48 23 13

 

New documents listed below were uploaded to the Documents section:

  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [9]
  • Building Plan Approval / NA Order for plotted development [39]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [3]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances [5]
  • Disclosure of sold/ booked inventory [6]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [10]
  • Other
  • Other – Technical
  • Proforma of Allotment letter