MH
Mumbai Suburban
P51800031310
RERA ID: P51800031310
Project Name: Piramal Revanta - Tower 4
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Mulund West, Mulund Goregaon Link Rd, Kurla, Mumbai Suburban-400080

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CTS No 491 A/5, 491 A/6, 491 A pt, 491 A/4 Pt

Boundaries:
N1150 E1158
N1132 E1122N N1178 E1145
WE
S
N1160 E1108

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 46890 sq.mt.
Sanctioned Built-up Area: 18744 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 44
No. of basements: 1
No. of Plinths: 1
No. of Closed Parking: 250

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 473 sq ft 113 65
2BHK 473 to 624 sq ft 188 176
3BHK 1022 to 1054 sq ft 17 16
Project Developer:
PRL Developers Private Limited
Organization Type: Company

Address: 8Th Floor, Piramal Tower, Ganpatrao Kadam Marg, Lower Parel (W), Peninsula Corporate Park, Mumbai City-400001

Office Phone: +91 22335 14000
Website URL: www.piramalrealty.com


Member details:
Member Name Designation
Jitesh Mirjolkar Authorized Signatory
Deepak suvarna Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Sandeep Shikre & Asso. Architect
Gleeds Consulting India Pvt Ltd Engineer
D. B. KETKAR & CO. Chartered Accountant


Projects in the state by this developer:
P51800054164 - Piramal Revanta Tower 5 - Mumbai Suburban
P51800031310 - Piramal Revanta - Tower 4 - Mumbai Suburban
P51800018099 - Piramal Revanta - Tower 3 - Mumbai Suburban
P51800014021 - Piramal Revanta - Tower 2 - Mumbai Suburban
P51800005983 - Piramal Revanta - Tower 1 - Mumbai Suburban
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

A New Horizon in Urban Living: Introducing Piramal Revanta - Tower 4

Piramal Revanta - Tower 4, a brand new residential project by PRL Developers Private Limited, promises to redefine luxury living in the heart of Mumbai. Located in the thriving neighborhood of Mulund West, this project offers a unique opportunity to own a slice of the city’s vibrant future.

Registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under ID P51800031310, Piramal Revanta - Tower 4 boasts a prime location on Mulund Goregaon Link Road. Situated on a spacious plot spanning 46890 square meters, the project comprises a single towering structure reaching 44 floors, designed to provide residents with unparalleled views and a sense of serenity amidst the urban bustle.

The project offers a diverse range of apartments, catering to various lifestyle preferences. From compact and stylish 1BHK units starting at 473 square feet to spacious 2BHK units ranging from 559 to 570 square feet, there’s an apartment to suit every need. Additionally, the project includes a single 3BHK unit spanning 936 square feet, perfect for families seeking ample space and luxury.

The project is meticulously designed to offer a comprehensive range of amenities, including a dedicated basement and plinth level, along with a convenient 250-car closed parking facility. While the project currently lacks designated recreational open space, the sheer size of the plot and its prime location provide ample opportunity for residents to explore the surrounding areas and enjoy the city’s vast green spaces.

With a projected completion date of March 31, 2026, Piramal Revanta - Tower 4 represents a compelling investment opportunity. The project is backed by the reputable PRL Developers Private Limited, renowned for their commitment to quality and innovation. Their dedication to customer satisfaction is evident in their detailed project plan, which is available for review on their website, www.piramalrealty.com.

Piramal Revanta - Tower 4 is more than just a residence; it’s an invitation to embrace a lifestyle characterized by comfort, convenience, and a vibrant community. This project promises to be a landmark development in Mulund West, setting a new standard for urban living in Mumbai.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 44 113 65
2BHK 44 1 0
2BHK 53 44 36
2BHK 56 71 68
2BHK 57 32 32
2BHK 58 40 40
3BHK 95 1 1
3BHK 98 16 15

 

New documents listed below were uploaded to the Documents section:

  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Other
  • 13 Other
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • 12 Disclosure of sold/ booked inventory
  • 13 Disclosure of sold/ booked inventory
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 86
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 88
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 92
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
1 Overall Percentage of Completion of the work done For the entire Building /Wing 85.1

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Supply : 70 a part of larger layout
Community Buildings : 60 Clubhouse a part of larger layout
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 a part of larger layout
Storm Water Drains : 100 a part of larger layout
Electrical Meter Room, Sub-Station, Receiving Station : 70 a part of larger layout
Internal Roads & Footpaths : 70 a part of larger layout

 

New documents listed below were uploaded to the Documents section:

  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 20 a part of larger layout
Sewerage (Chamber, Lines, Septic Tank , STP) : 5 a part of larger layout

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 44 129 61
2BHK 52 132 115

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 72
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 64
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
1 Overall Percentage of Completion of the work done For the entire Building /Wing 74.6

 

New documents listed below were uploaded to the Documents section:

  • 11 Other
  • 11 Disclosure of sold/ booked inventory
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 3 Details of encumbrances
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 44 129 48
2BHK 52 132 89
2BHK 53 72 72

 

New documents listed below were uploaded to the Documents section:

  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 10 Other
  • 10 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [8]
  • Building Plan Approval / NA Order for plotted development [5]
  • CERSAI details [2]
  • Commencement Certificates / NA Order for plotted development [7]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances [2]
  • Disclosure of sold/ booked inventory [9]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) [3]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [8]
  • Other [9]
  • Proforma of Allotment letter [2]