MH
Mumbai Suburban
P51800024892
RERA ID: P51800024892
Project Name: AVRON V
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-12-29
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2023-12-30).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Chembur East, Plot No. 298A, Cts No. 1609, 5Th Road, Kurla, Mumbai Suburban-400071

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 298A, CTS NO. 1609

Boundaries:
CTS 1610
CTS 1608N 5TH ROAD
WE
S
CTS 1605

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 480 sq.mt.
Sanctioned Built-up Area: 1296 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 11
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 5
No. of Closed Parking: 18

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
4BHK 1321 sq ft 4 2
Project Developer:
AVRON REALTY LLP
Organization Type: Partnership

Address: Plot No 594, 1St Floor, Padma, 21St Road, Bandra West, Greater Mumbai (M Corp.) (Part) (802794), Mumbai, Mumbai Suburban-400052

Office Phone: +91 22252 83182


Member details:
Member Name Designation
SANJAY GEHIMAL DEVNANI Authorized Signatory
SANJAY GEHIMAL DEVNANI Partner
RAVI GOPAL HARISINGANI Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
BIMAL RAI KOCHHAR Individual Area Share
RAJESH KOCHHAR Individual Area Share


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Unveiling AVRON V: A New Residential Development in Chembur East

AVRON V, a new residential project by AVRON REALTY LLP, is set to transform the landscape of Chembur East, Mumbai. This project, registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under the ID P51800024892, promises to deliver high-quality, spacious living spaces in a prime location.

Located on PLOT NO 298A, CTS NO. 1609, 5TH ROAD, AVRON V occupies a sprawling 480 sq. meters of land. The project comprises a single building with 11 sanctioned floors and a stilt floor, offering a total sanctioned built-up area of 1296 sq. meters. With a focus on efficient space utilization and modern design, the project offers a limited selection of 4 BHK apartments, each spanning 1321 sq. ft.

The project is strategically located in Chembur East, a thriving residential hub in Mumbai. Its proximity to major roads and public transportation options ensures excellent connectivity. Additionally, residents will have easy access to a range of amenities, including shopping centers, educational institutions, healthcare facilities, and entertainment venues.

The project prioritizes resident comfort and convenience. AVRON V features a blend of open and closed parking spaces to accommodate 5 four-wheelers and 18 two-wheelers, ensuring safe and convenient parking for residents. The project also boasts a meticulously designed common area that enhances the overall living experience.

While the project is currently under construction, AVRON REALTY LLP is committed to delivering the project by December 29th, 2024. The project has received all necessary approvals from the relevant authorities and is free from any ongoing litigations. With a strong track record and a commitment to excellence, AVRON REALTY LLP is poised to deliver a high-quality residential development that meets the needs of modern homebuyers.

For potential homebuyers seeking spacious, well-designed apartments in a prime location, AVRON V represents an exciting opportunity. Interested individuals are encouraged to contact AVRON REALTY LLP for further information and to explore the various options available at this promising new development.

The project record has been corrected for the District it is located in, a rare occurance. The new value for District is Mumbai Suburban

 

A correction has been made to the Developer’s address. The complete address is now: Plot No 594, 1St Floor, Padma, 21St Road, Bandra West, Greater Mumbai (M Corp.) (Part) (802794), Mumbai, Mumbai Suburban-400052

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 100

 

New documents listed below were uploaded to the Documents section:

  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Architect’s Certificate on Completion of Project (Form 4)

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory

 

New documents listed below were uploaded to the Documents section:

  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 90

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
4BHK 122.76 4 2

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-12-29

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Declaration about Commencement Certificate
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Disclosure of sold/ booked inventory

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Solid Waste Management And Disposal : 100 AS PER NOC
Landscaping & Tree Planting : 100 AS PER TREE NOC
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 AS PER NOC
Water Supply : 100 GRAVITY BASED WATER SUPPLY SYSTEM IS PROPOSED
Fire Protection And Fire Safety Requirements : 100 FIRE FIGHTING AND DETECTION SYSTEMS AS PER CFO NOC
Water Conservation, Rain water Harvesting : 100 AS PER NOC
Electrical Meter Room, Sub-Station, Receiving Station : 100 III PHASE ELECTRIC METER

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 88

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of Interest in Other Real Estate Organizations
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [3]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Other
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal