Project Name: Avis Residency
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2024-10-31
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2019-12-31, 2014-11-30).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
, Kurla, Mumbai Suburban-400077

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
222

Boundaries:
Plot No 221
Plot No 214 215 216N R N Narkar Marg
WE
S
Plot no 223

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 1673 sq.mt.
Sanctioned Built-up Area: 4293 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 16
No. of Plinths: 1
No. of Podiums: 1
No. of Stilts: 1
No. of Open Parking: 2
No. of Closed Parking: 78

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 779 to 781 sq ft 8 7
3BHK 930 to 994 sq ft 21 19
Shop 390 to 1199 sq ft 2 2
Project Developer:
Avi housing Realtors
Organization Type: Partnership

Address: 1, Avis Vraj A Paradise, Garden Lane, Sanghani Estate, Shreyas Cinema, Kurla, Mumbai Suburban-400086

Office Phone: +91 22250 00056


Member details:
Member Name Designation
Paresh Vrajlal Chabhadia Partner
Priyank Chetan Chabhadia Partner
Paresh Vrajlal Chabhadia Authorized Signatory


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Avis Residency: A Residential Project in the Heart of Kurla

Avis Residency, a project developed by Avi Housing Realtors, presents a unique opportunity for homebuyers seeking a comfortable and modern living space in the bustling locality of Kurla, Mumbai. Located within the Sanghani Estate, the project boasts a prime location near the landmark Shreyas Cinema, ensuring excellent connectivity and accessibility.

This ongoing residential project, registered with RERA under ID P51800012791, is strategically situated on plot number 222, spanning a total area of 1673 square meters. The project comprises a single building with 16 sanctioned floors, including a stilt floor and a podium. Avis Residency offers a variety of unit configurations, including 2BHK, 3BHK apartments, and shop spaces, catering to diverse lifestyle needs.

The project, initially scheduled for completion in November 2014, experienced delays and subsequently revised its completion date to December 2019. Further extensions were granted, with the current expected completion date set for February 2024. Despite these delays, the project is currently progressing smoothly and is free from any legal disputes.

While the project features a limited number of open parking spaces (2), it offers a substantial 78 closed parking options, ensuring convenient parking for residents. Although the project doesn’t offer dedicated recreational open space, its strategic location and proximity to amenities within Sanghani Estate provides residents with ample opportunities for leisure and entertainment.

Avi Housing Realtors, a partnership firm with a proven track record, is committed to delivering a high-quality residential experience. The project’s focus on practical and functional design, coupled with its prime location, promises residents a comfortable and convenient lifestyle.

Avis Residency is more than just a residential project; it is an opportunity to own a piece of Kurla’s thriving community, offering residents a blend of urban convenience and modern living.

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-10-31

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Fire Protection And Fire Safety Requirements : 50 after completion of Building
Water Conservation, Rain water Harvesting : 0 After completion of building
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 after completion of Building
Water Supply : 100
Electrical Meter Room, Sub-Station, Receiving Station : 80 after completion of Building

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 22 19 85
Covered Parking ( In Numbers) 95 79 50

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 X number of Podiums 100
1 Stilt Floor 100
1 X number of Slabs of Super Structure 95
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 81.5

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 72.46 7 6
2BHK 72.59 1 1
3BHK 86.44 8 8
3BHK 88.08 7 6
Shop 111.48 1 1
Shop 36.29 1 1

 

New documents listed below were uploaded to the Documents section:

  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

New documents listed below were uploaded to the Documents section:

  • 3 Declaration in FORM B
  • 2 Declaration in FORM B

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 4 CERSAI details
  • 3 CERSAI details
  • 2 CERSAI details
  • 1 CERSAI details

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 72.46 8 7
Shop 115.83 1 1
Shop 35.55 1 1

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Fire Protection And Fire Safety Requirements : 75 after completion of Building
Electrical Meter Room, Sub-Station, Receiving Station : 75 after completion of Building
Water Supply : 75
Sewerage (Chamber, Lines, Septic Tank , STP) : 80 after completion of Building

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [2]
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development [2]
  • Other
  • Proforma of Allotment letter